首页
登录
从业资格
Estimating schedule activity costs invol
Estimating schedule activity costs invol
admin
2022-08-02
31
问题
Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of theA.project scope statement B.statement of work C.project management plan D.project policy
选项
A.project scope statement
B.statement of work
C.project management plan
D.project policy
答案
A
解析
估算计划活动的成本涉及估算完成每项计划活动所需资源的近似成本,成本估算包括设别和考虑各种成本计算方案。例如:在多数的应用领域,普遍在设计阶段多做些额外工作以降低在执行阶段和产品运行时的潜在成本。成本估算过程考虑预期的成本节省是否能够弥补额外设计工作的成本。成本估算一般是以货币单位表示,以利于在项目内和项目间进行比较,项目范围说明书描述了项目的商业要求、理由、需求和当前边界,它提供了关于在成本估算时必须考虑的项目需求的重要信息。
转载请注明原文地址:https://tihaiku.com/congyezige/2295903.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
Theprojectscheduleismorethanadocu
Scheduledevelopmentcanrequiretherev
Theprojectscheduleismorethanadocu
果在一个课程注册系统中,定义了类CourseSchedule和类Course,并
Ascheduleiscommonlyusedinprojectp
Scheduledevelopmentcanrequiretherev
Scheduledevelopmentcanrequiretherev
()isatechniqueforestimatingthedu
EstimateActivityDurationsistheproce
随机试题
Whatdoesthewomanthinkaboutthebusinessoftheman?[br][originaltext]W:
[originaltext]Asexpertswarnofacomingfoodcrisis,theverticalfarming
下列单位中哪一个是用于表示无功功率的单位?( )A.kW B.kV C.k
胫骨内侧髁下方至内踝尖的骨度分寸是A、13寸 B、14寸 C、16寸 D、
Thechangeinthatvillagewasmiraculou
以下具有昙点的表面活性剂是A:Span80 B:Tween80 C:卵磷脂
按皮亚杰的观点,以自我为中心,单方面考虑问题的儿童处于()。A.感觉运动期
儿童心理发展潜能的主要标志是( )。A、最近发展区的大小 B、潜伏期的长短
A.医务人员疏忽大意违反卫生法律相关规定,给患者造成明显人身伤害 B.医务人员
政府对工程质量监督的行为从性质上属于()。A.技术服务 B.委托代理 C.行
最新回复
(
0
)