首页
登录
从业资格
The project schedule is more than a docu
The project schedule is more than a docu
免费题库
2022-08-02
66
问题
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record
选项
答案
B
解析
项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来()。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录
转载请注明原文地址:https://tihaiku.com/congyezige/2301715.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
( )isameasureofscheduleperformance
Thecustomerasksyourprojecttobecom
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
Whyisthespeakercalling?[originaltext]Hey,Carlos.ThisisDanielYu,andl
Beforehisdeathlastyear,ProfessorJohnsondecidedthathe______leave$2,000
[originaltext]M:HiTracy!Whatdoyouthinkofourclassonchildren’sliterat
企业对该资产负债表日后调整事项进行会计处理时,下列报告年度财务报表项目中,不应调
A.A→B B.B→C C.A→B和B→C都是 D.A→B和B→C都不是
反射光线从靠近入射光线的反方向,向光源返回的反射称逆反射。
下列说法有误的是()。A.新型农村合作医疗基金支出逐年增加 B.参
关于企业市场调查的说法,错误的是( )。A.市场调查是企业认识市场的活动 B
(2015年真题)可用于减缓区域地下水过量开采的措施有()。A.地面防渗
下列关于堆石坝面板施工方法的描述,正确的是()。A.混凝土面板宜采用单层双
最新回复
(
0
)