首页
登录
从业资格
The project schedule is more than a docu
The project schedule is more than a docu
免费题库
2022-08-02
28
问题
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record
选项
答案
B
解析
项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来()。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录
转载请注明原文地址:https://tihaiku.com/congyezige/2301715.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
( )isameasureofscheduleperformance
Thecustomerasksyourprojecttobecom
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
Investmentinthepublicsector,suchaselectricity,irrigation,publicser
JonathanGlater,avisitingassistantprofessoroflawattheUniversityof
“五位一体”的监管体系中不包括()。A、证监局B、期货交易所C、期货公司D、中国期货业协会C“五位一体”的期货监管体系包括中国证监会、证监局、
土料摊铺检验时,铺料时应在设计边线外侧各超填一定余量,人工铺料宜大于( )cm
下列哪种疾病与输血无关()A.艾滋病 B.疟疾 C.梅毒 D.淋病
某些地方政府为了扩大自己的影响大搞劳民伤财、徒有虚表的“形象工程”,解决这一问题
下列中成药中,含有冰片的是A.开胸顺气丸 B.祛风止痛片 C.礞石滚痰丸
下列支气管扩张剂中哪种药物的作用时间最长A.沙丁胺醇B.特布他林C.沙美特罗D.
以下属于创造性思维特征的有()。 A.敏感性B.流畅性 C.灵活性D.
一个65岁的妇女以舌炎、体重减轻、感觉异常和腹泻来诊。实验室检查表明为巨细胞性贫
最新回复
(
0
)