首页
登录
从业资格
The project schedule is more than a docu
The project schedule is more than a docu
免费题库
2022-08-02
58
问题
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record
选项
答案
B
解析
项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来()。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录
转载请注明原文地址:https://tihaiku.com/congyezige/2301715.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
( )isameasureofscheduleperformance
Thecustomerasksyourprojecttobecom
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
•Youwillhearanotherfiverecordings.•Foreachrecording,decidewhatthes
Hishealthhasbeenaffected,andmay______altogetherifthestraincontinues.A、
Whichofthefollowingsentenceisanellipticalsentence(省略句)?A、Onthetopoft
ErnestHemingwaywasmostfamousfor______.A、TheSeaandtheOldManB、Theold
Menbelievethattheyarebetterandclevererthanwomenbecause______.[br]On
Tosaythatthechildlearnsbyimitationandthatthewaytoteachistose
Sleepisveryancient.Intheelectroencephalographic(脑电图仪的)senseweshare
A.Moberg拾物试验 B.Carroll手功能评定法 C.明尼苏达操作等
A.婴儿期B.幼儿期C.学龄前期D.学龄期E.青春期不对小儿学习成绩有过多要求,
特种作业是指在劳动过程中容易发生伤亡事故,对操作者本人,尤其对他人和周围设施的安
最新回复
(
0
)