首页
登录
从业资格
The project schedule is more than a docu
The project schedule is more than a docu
免费题库
2022-08-02
67
问题
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record
选项
答案
B
解析
项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来()。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录
转载请注明原文地址:https://tihaiku.com/congyezige/2301715.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
( )isameasureofscheduleperformance
Thecustomerasksyourprojecttobecom
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
Whohasgotapen?[br][originaltext]M:Excuseme,LiPing.MayIborrowyour
ThousandsofyearsbeforeColumbuscametotheNewWorld,theAmericanIndian
NoEnglishmanbelievesinworkingfrombooklearning.Hesuspectseverything
[originaltext]M:Goodmorning,class.W:Goodmorning,sir.M:Todaywe’lldisc
严重腹泻可以引起A.肾脏对NaHCO{图}重吸收代偿降低B.胃酸损失C.碳酸氢盐
(2019年真题)按信托财产的不同,可将信托划分为()。A.动产信托 B
与氨代谢有关的代谢是( )。A.三羧酸循环 B.鸟氨酸循环 C.蛋氨酸循环
高血压病的动脉系统病变期,小动脉的病变是A.粥样硬化 B.破裂出血 C.间歇
6个月,男婴,人工喂养。平时易惊、多汗、睡眠少,近2日来咳嗽、低热,今晨突然双眼
(2017年真题)在建设工程项目施工过程中,施工机具使用费的索赔款项包括( )。
最新回复
(
0
)