首页
登录
从业资格
The project schedule is more than a docu
The project schedule is more than a docu
免费题库
2022-08-02
73
问题
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record
选项
答案
B
解析
项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来()。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录
转载请注明原文地址:https://tihaiku.com/congyezige/2301715.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
( )isameasureofscheduleperformance
Thecustomerasksyourprojecttobecom
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
•Readthearticlebelowaboutsuccessfule-mailnegotiation.•Choosethebestse
HowcanEnglishteachersacceleratethelanguagelearningoftheirstudents?
Onceitwaspossibletodefinemaleandfemaleroleseasilybythedivision
Everybodysleeps,butwhatpeoplestayuplatetocatch—orwakeupearlyin
操作系统是一种对()进行控制和管理的系统软件。A.应用程序 B.全部硬件资
《中华人民共和国消费者权益保护法》第6条规定,保护消费者的合法权益是()的共同责
下列关于审计人员选择审计标准的做法,错误的是:A:考虑审计标准的适用性,应选择适
C解题指导:每个图形的笔画数都为8,故答案为C。
与吸附力最相关的因素是A.义齿基托组织面与黏膜接触的密合程度 B.唾液的质和量
关于缺陷责任期与保修期的说法,正确的有()。A.缺陷责任期满后,应当返还质量保
最新回复
(
0
)