首页
登录
从业资格
The project schedule is more than a docu
The project schedule is more than a docu
免费题库
2022-08-02
45
问题
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record
选项
答案
B
解析
项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来()。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录
转载请注明原文地址:https://tihaiku.com/congyezige/2301715.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
( )isameasureofscheduleperformance
Thecustomerasksyourprojecttobecom
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
DreamResearchshowsthateveryonedreamsqui
AccordingtoEllen,theincreasingdemandforhiringisdueto[br][originalte
EducatingPsychebyBernieNevilleisabookwhichlooksatradicalnewappr
[originaltext]Manyteachersbelievethattheresponsibilityforlearningli
[originaltext]W:Hey,Bob,guesswhat?I’mgoingtovisitQuebecnextsummer.I
根据《陕西省建设工程工程量清单计价规则》,项目编码的后三位反映不同的( )。A
CFA提出了最佳执行的实施框架,不属于的一项是()。A.披露 B.过程 C
沥青混凝土路面不平整的预防措施有()。A.压路机用较小的振频、振幅进行碾压
某配电装置室长8m,应设置()个出口,并宜()。两,对称布置在配电室中段
企业会计期间分为()A.年度 B.季度 C.中期
最新回复
(
0
)