Schedule development can require the rev
Schedule development can require the rev
练习题库
2022-08-02
58
问题
Schedule development can require the review and revision of duration estimates and resource estimates to create an approved () that can serve as a baseline to track progress.A.scope statementB.activity listC.project charter D.project schedule
选项
A.scope statement
B.activity list
C.project charter
D.project schedule
答案
D
解析
计划进展需要对持续时间和资源的评估和修改创建一个被核准的(74),它可以作为基线,有助于跟踪进展。A.范围说明B.活动列表C.项目章程 D.项目计划
转载请注明原文地址:https://tihaiku.com/congyezige/2299676.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
TheSystemsDevelopmentLifeCycle(SDLC
如果在一个课程注册系统中,定义了类CourseSchedule和类Course,
Theprojectscheduleismorethanadocu
Ascheduleiscommonlyusedinprojectp
Theprojectscheduleismorethanadocu
TheSystemsDevelopmentLife Cycle(SDL
Ascheduleiscommonlyusedinprojectp
TheSystemsDevelopmentLifeCycle(SDLC
Scheduledevelopmentcanrequiretherev
Theschedulemanagementplanisacompon
随机试题
LookattheOfficeplanbelow.Forquestions6—10,whodoesthesejobs?
A)Inthisarticle,we’lllookattherulesfor529QualifiedStateTuition
地籍平面控制点相对于起算点的点位中误差不超过( )cm。A.±3 B.±5
2020年国内游客28.8亿人次,比上年下降52.1%。其中,城镇居民游客20.
研究表明,美国和德国的青少年把父母的限制性管教方式看作是讨厌自己,而在韩国和日本
(2021年真题)小美因丈夫出轨而伤心不已,患上了中度抑郁症。在与社会工作者小杨
A.息风止痉 B.活血消肿 C.疏散风热 D.利尿通淋 E.凉血止痢鱼腥
根据《标准施工招标文件》(2007年版),下列情形中,应由发包人承担由此增加的费
箱涵顶进冬期施工时,应确保混凝土()满足规范规定或设计要求。A.砂率 B.入
A.第6~8周 B.第10周 C.第32~34周 D.第34~36周 E
最新回复
(
0
)