Schedule development can require the review and revision of duration estimates and resource estimates to create an approved ( ) that can serve as a baseline to track progress.A.scope statementB.activity listC.project charterD.project schedule
选项
A.scope statement
B.activity list
C.project charter
D.project schedule
答案
D
解析
计划进展需要对持续时间和资源的评估和修改创建一个被核准的 项目计划,它可以作为基线,有助于跟踪进展。
转载请注明原文地址:https://tihaiku.com/congyezige/2302028.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isameasureofscheduleperformance
如果在一个课程注册系统中,定义了类CourseSchedule和类Course,
Theprojectscheduleismorethanadocu
TheSystemsDevelopmentLifeCycle(SDLC
Theprojectscheduleismorethanadocu
果在一个课程注册系统中,定义了类CourseSchedule和类Course,并
Theprojectscheduleismorethanadocu
Ascheduleiscommonlyusedinprojectp
TheSystemsDevelopmentLifeCycle(SDLC
Scheduledevelopmentcanrequiretherev
随机试题
Youwillhearachairmandeliveringareportatanannualconferencewhichw
Thereisarangeofactivitieswhichrequiremovementsofaboutonetofour
SimonFanshawepresentsdifferentpeople’sopinionsonBritishmannersbecause__
SuggestionsforImprovingReadingSpeedImprovemento
Mostearthquakesoccurwithintheupper15milesoftheearth’ssurface.Butear
D
醋酸铵在水中存在着如下平衡:NH3+H2O===NH+4+OH-……K1H
下列配伍关系中,性能功效相类似的药物配合应用,可增强原有疗效的是A:相使B:相
下列各句中,加点的成语使用恰当的一项是()。A. B. C. D.
有甲乙两个方案,如果选择其中一个方案,不影响另外一个方案的选择,方案采用与否取决
最新回复
(
0
)