Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.A.scope statementB.activity listC.project charterD.project schedule
选项
A.scope statement
B.activity list
C.project charter
D.project schedule
答案
D
解析
计划进展需要对持续时间和资源的评估和修改创建一个被核准的(74),它可以作为基线,有助于跟踪进展。
A. 范围说明 B. 活动列表 C. 项目章程 D. 项目计划
转载请注明原文地址:https://tihaiku.com/congyezige/2299734.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Ascheduleiscommonlyusedinprojectp
Scheduledevelopmentcanrequiretherev
Scheduledevelopmentcanrequiretherev
Theprojectscheduleismorethanadocu
TheDevelopmentofProjectManagementPl
TheSystemsDevelopmentLife Cycle(SDL
Scheduledevelopmentcanrequiretherev
Ascheduleiscommonlyusedinprojectp
Scheduledevelopmentcanrequiretherev
Theschedulemanagementplanisacompon
随机试题
PriortobecomingacomputerprogrammeratJasperCompany,Mr.Rogers______asa
Asalways,IampleasedtobehereattheNationalPressClubformy(1)Spe
[audioFiles]audio_ehbz20076_002(20076)[/audioFiles]A、Warm.B、Cold.C、Hot.D、Wet
适用深埋于岩体的长隧洞施工的方法是()。A:顶管法 B:TBM法 C:盾构
水解反应后可变为绿色的是A.黄芩苷 B.木樨草素 C.大豆素 D.杜鹃素
下列关于失业率的说法中,正确的有()。 Ⅰ.失业率是指劳动力人口中失业人数
无意注意与有意注意是()。A、没有关系的 B、不能转化的 C、可以转化的
唐朝的五刑一共( )。 A.二十等 B.二十五等 C.十五等 D.十等
甲公司因扩建需要购买大型设备一台,遂向专门从事大型设备出租的乙公司提出要求租赁丙
对已进场经检验不合格的工程材料,项目监理机构应要求施工单位将该批材料()。A.
最新回复
(
0
)