首页
登录
从业资格
A schedule is commonly used in project p
A schedule is commonly used in project p
资格题库
2022-08-02
73
问题
A schedule is commonly used in project planning and project portfolio management. ( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构(WBS)的最终元素( ),工作说明书,或合同数据需求清单密切相关。A.Essences精髓B.Elements元素C.Purposes目的D.Issues问题
选项
A.Essences精髓
B.Elements元素
C.Purposes目的
D.Issues问题
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299997.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inaprojectplan,whentheprojectmana
ProjectIntegrationManagementincludes
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
WhichofthefollowingProjectScopeMan
随机试题
[originaltext]M:HiHelen.Whatdoyouthinkofourclassinchildren’sliterat
[originaltext]Badnewsforthedeliveryguys:youmighthavetostartthink
[originaltext]Thepurposeofkeepingfitistoavoidiiihealth,resistthe
Theuseofnuclearpowerhasalreadyspreadallovertheworld.【C1】______,s
4×400米接力比赛为部分分道跑,运动员跑完几个弯道后切入里道(??)A.4个
在内部控制良好的情况下,收到商品时,负责验收人员应当与商品进行核对的原始凭证为(
基金年底报告披露的财务指标中,能够较为,合理地评价基金业绩表现的指标是()
A.ab B.cb C.lb D.lc
2019年10月,向某为自己17周岁的儿子投保了一份以死亡为给付保险金条件的合同
关于不当或违法代理行为应承担法律责任的说法,正确的有( )。A.第三人明知代理
最新回复
(
0
)