首页
登录
从业资格
A schedule is commonly used in project p
A schedule is commonly used in project p
资格题库
2022-08-02
31
问题
A schedule is commonly used in project planning and project portfolio management. ( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构(WBS)的最终元素( ),工作说明书,或合同数据需求清单密切相关。A.Essences精髓B.Elements元素C.Purposes目的D.Issues问题
选项
A.Essences精髓
B.Elements元素
C.Purposes目的
D.Issues问题
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299997.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inaprojectplan,whentheprojectmana
ProjectIntegrationManagementincludes
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
WhichofthefollowingProjectScopeMan
随机试题
TheAuthorizedVersionoftheBible(publishedin1611)wasmadeby______command
WhichnumberisconsideredanunluckynumberintheWest?______isconsidereda
Shedecidedtodevoteherself______theproblemofoldage.A、tostudyB、studying
WepartedtwentyyearsagoandIhavebe
颅骨骨缝的生长发育主要可以引起下述哪项指标的改变A.面宽 B.上颌骨长度 C
前列腺增生的易发部位A.央区 B.外周区 C.移行区 D.整个腺体
关于碾压混凝土坝施工质量控制的说法,正确的是()。A.碾压混凝土坝一般采用V
共用题干 Ha!TheSdenceofWhenWeLaughand
Thechangeinthatvillagewasmiraculou
有一建造于Ⅱ类场地上的钢筋混凝土多层框架,抗震等级为二级,其中某柱的轴压比为0.
最新回复
(
0
)