首页
登录
从业资格
A schedule is commonly used in project p
A schedule is commonly used in project p
资格题库
2022-08-02
62
问题
A schedule is commonly used in project planning and project portfolio management. ( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构(WBS)的最终元素( ),工作说明书,或合同数据需求清单密切相关。A.Essences精髓B.Elements元素C.Purposes目的D.Issues问题
选项
A.Essences精髓
B.Elements元素
C.Purposes目的
D.Issues问题
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299997.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inaprojectplan,whentheprojectmana
ProjectIntegrationManagementincludes
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
WhichofthefollowingProjectScopeMan
随机试题
TheFrenchdivisionofMcDonald’shasrunadvertisementsthatincludedasur
Unlessmeasuresaretakenatonce,thereisapossibilitythatalltheocean
CPU的工作周期为20ns,主存存取周期为10ns,此时DMA接口适合采用()方
当采用龙门桅杆滑移法吊装时,其上部横梁的改制要符合国家的有关标准要求,焊缝应作(
1.事故经过 5月2日,刘某组织人员在项目现场西3门前开始搭设脚手架。当脚
患者,女,9岁,右上中切牙萌出已经两年,两侧侧切牙萌出正常,左上乳中切牙不松动,
患者女,38岁,未婚。因经量增多20余天,今日出血顺腿流,伴昏厥1次来院。既往月
试讲题目Lastweekend
A.穿山甲B.安息香C.乌贼骨D.大腹子E.元寸海螵蛸的别名是
最新回复
(
0
)