Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources . The tools and technques is not including().A、expert judgmentB、analogous estimatingC、requirements traceability matrixD、three-point estimating
选项
A、expert judgment
B、analogous estimating
C、requirements traceability matrix
D、three-point estimating
答案
C
解析
估算活动持续时间是估算完成具有估计资源的个体的工作时间的过程。下列哪个工具和技术(需求跟踪矩阵)不包括在内。
A、专家判断
B、类比估算
C、需求跟踪矩阵
D、三点估算
转载请注明原文地址:https://tihaiku.com/congyezige/2298072.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
Thoseitemsareoftenestimatedinterms
Thoseitemsareoftenestimatedinterms
EstimateActivityDurationsistheproce
Estimatingactivity durationsusesinfo
TheEstimateActivityResourceprocessi
Estimatingscheduleactivitycostsinvol
EstimateActivityDurationsistheprocessofe
随机试题
Thespaceshuttle【D1】______madeararenightlandingattheKennedySpaceC
ABCDEFGHWhatletteristwototherightoftheletterwhichisfourtotheleft
在统计学中称()为统计功效,又翻译为统计检验力。A.α B.l-α C.1
横膈与脾脏之间出现液性暗区,最常见于A.膈下脓肿 B.胸腔积液 C.包膜下血
下列不属于欺诈客户的是( )。 Ⅰ.基金从业人员在宣传、推介和销售基金产品时
肿物赘生于人体,坚硬如石,形状不规则的称之为A.疔 B.瘤 C.岩 D.疽
《医疗机构管理条例、医疗机构管理条例实施细则、麻醉药品管理法》、《医疗事故处理条
健康传播是一种将医学研究成果转化为大众的健康知识。并通过大众生活态度和行为方式的
测量结果受到多种因素的影响。为了达到测量的预定要求,测量仪器必须具有符合规范要
市盈率的计算公式为:市盈率=股票市场价格/每股净资产。()
最新回复
(
0
)