Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources . The tools and technques is not including().A、expert judgmentB、analogous estimatingC、requirements traceability matrixD、three-point estimating
选项
A、expert judgment
B、analogous estimating
C、requirements traceability matrix
D、three-point estimating
答案
C
解析
估算活动持续时间是估算完成具有估计资源的个体的工作时间的过程。下列哪个工具和技术(需求跟踪矩阵)不包括在内。
A、专家判断
B、类比估算
C、需求跟踪矩阵
D、三点估算
转载请注明原文地址:https://tihaiku.com/congyezige/2298072.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
Thoseitemsareoftenestimatedinterms
Thoseitemsareoftenestimatedinterms
EstimateActivityDurationsistheproce
Estimatingactivity durationsusesinfo
TheEstimateActivityResourceprocessi
Estimatingscheduleactivitycostsinvol
EstimateActivityDurationsistheprocessofe
随机试题
Theexpertsays______inperformancecanbeappliedsuccessfullytoapolitical
Losingajobornotbeingabletofindonealmostalwaysbringsunwelcomech
Thegrowthofpopulationduringthepastfewcenturiesisnoproofthatpopu
创新思路,加强领导,确保在学生党组织和党员中深入开展创先争优活动取得实效,积极探
电影院、KTV、溜冰场均设置在多层商店建筑内,则该疏散楼梯间按()的要求进
当旅游者因无心之过出现与旅游目的地风俗习惯不协调的行为时,领队应( )。A.及时
虚劳患者,短气自汗,声音低怯,时寒时热,平素易于感冒,舌质淡,脉弱。其证候是A.
证券公司在向客户融资融券前签订的融资融券业务合同中乙方(指证券公司)信息不包括(
(2018年真题)一级公路水泥稳定土路面基层施工,适宜的方法为()。A.厂拌法
发明专利权的期限,自()起计算。A.申请日 B.商标局收到申请书 C.公告发
最新回复
(
0
)