Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources . The tools and technques is not including().A、expert judgmentB、analogous estimatingC、requirements traceability matrixD、three-point estimating
选项
A、expert judgment
B、analogous estimating
C、requirements traceability matrix
D、three-point estimating
答案
C
解析
估算活动持续时间是估算完成具有估计资源的个体的工作时间的过程。下列哪个工具和技术(需求跟踪矩阵)不包括在内。
A、专家判断
B、类比估算
C、需求跟踪矩阵
D、三点估算
转载请注明原文地址:https://tihaiku.com/congyezige/2298072.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
Thoseitemsareoftenestimatedinterms
Thoseitemsareoftenestimatedinterms
EstimateActivityDurationsistheproce
Estimatingactivity durationsusesinfo
TheEstimateActivityResourceprocessi
Estimatingscheduleactivitycostsinvol
EstimateActivityDurationsistheprocessofe
随机试题
Foreachofthefollowingfunctions,givethedomainandadescriptionofthegr
CableTVhasexperiencedtremendousgrowthasanadvertisingmediumbecause
Probablyforaslongastherehavebeensalesforces,managershavesought
By______wemeanlanguagecommunicationisconstrainedbyneithertimenorspac
以张伟的名义于2006年12月30日写一封投诉信。信中应包括以下内容:1.一周前买的型号为X2000乐人牌MP3播放器,使用一周内效果良好;今晨一开
按占有者身份划分,中国园林的类型有( )A.皇家园林 B.私家园林 C.北方
氧气雾化吸入时,正确的是A.病人呼气时用手指堵住出气管 B.药液应稀释在10m
下列各句中没有语病的一句是()。A.达尔文学说认为,不仅一切生物都是进化来的,
(2020年真题)根据《商业银行并购贷款风险管理指引》(银监发(2015]5号)
某医师治疗风寒湿痹,常用中成药小活络丸(大蜜丸)。该药处方有制川乌、制草乌、醋乳
最新回复
(
0
)