Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources . The tools and technques is not including().A、expert judgmentB、analogous estimatingC、requirements traceability matrixD、three-point estimating
选项
A、expert judgment
B、analogous estimating
C、requirements traceability matrix
D、three-point estimating
答案
C
解析
估算活动持续时间是估算完成具有估计资源的个体的工作时间的过程。下列哪个工具和技术(需求跟踪矩阵)不包括在内。
A、专家判断
B、类比估算
C、需求跟踪矩阵
D、三点估算
转载请注明原文地址:https://tihaiku.com/congyezige/2298072.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
Thoseitemsareoftenestimatedinterms
Thoseitemsareoftenestimatedinterms
EstimateActivityDurationsistheproce
Estimatingactivity durationsusesinfo
TheEstimateActivityResourceprocessi
Estimatingscheduleactivitycostsinvol
EstimateActivityDurationsistheprocessofe
随机试题
Althoughmostpeoplereturnfrompackageholidaysreasonablysatisfied,this
[originaltext]W:Mywatchstoppedagain.AndIjustgotanewbattery.Thatmad
[originaltext]W:IdrivenowbutIdidn’tuseto.M:Ihavedrivenfortwoyear
一个国家各级各类学校的总体系是指()。A.学校教育制度 B.国民教育制度 C
患者,男,32岁,在一次运动后,突然左腰部绞痛,相继出现肉眼血尿,左腰部有轻度压
某计算机主存容量为64KB,其中ROM区为4KB,其余为RAM区,按
砌砖前()天,应将砖浇水湿润。A.0.5 B.1 C.1~2 D.3
下列不属于急性肝炎患者临床表现的是A.疲倦乏力 B.肝病面容 C.肝区压痛
(2008年10月)简述个体身心发展的一般规律。
将SKF-525A给予实验动物后,发现苯转变为苯酚速率明显减慢,说明该物质抑制A
最新回复
(
0
)