问题 Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources . The tools and technques is not including().A、expert judgmentB、analogous estimatingC、requirements traceability matrixD、three-point estimating

选项 A、expert judgment
B、analogous estimating
C、requirements traceability matrix
D、three-point estimating

答案 C

解析 估算活动持续时间是估算完成具有估计资源的个体的工作时间的过程。下列哪个工具和技术(需求跟踪矩阵)不包括在内。
A、专家判断
B、类比估算
C、需求跟踪矩阵
D、三点估算