首页
登录
从业资格
( ) is a technique for estimating the du
( ) is a technique for estimating the du
考试题库
2022-08-02
55
问题
( ) is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.A. Analogous estimatingB. Parametric estimatingC. Three-Point estimatingD. Bottom-Up estimating
选项
A. Analogous estimating
B. Parametric estimating
C. Three-Point estimating
D. Bottom-Up estimating
答案
A
解析
是一种使用来自类似活动或项目的历史数据来估算活动或项目的持续时间或成本的技术。
A、类比估算
B、参数估算
C、三点估算
D、自下而上的估算
转载请注明原文地址:https://tihaiku.com/congyezige/2298146.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
()isaprojectmanagementtechniquefor
Theearnedvaluetechniqueisacommonly
Theearnedvaluetechniqueisacommonly
()isaprojectmangementtechniqueform
estimatingisatechniqueforestimating
Manyusefultoolsandtechniquesareuse
()estimatingisatechniqueforestimat
Estimatingactivity durationsusesinfo
The()techniqueinvolvesusingproject
()isoneofthetoolsandtechniquesof
随机试题
Whatdoesthewomanwanttoborrow?[br][originaltext]WomanIneedascrewdriv
Tostaywarmincoldweather,cold-bloodedanimalsmustexposeitselftoasourc
[originaltext]W:HowwasyourtriptoLondon?You’vebeentoBritainbefore,ha
Therelianceoncreditreportsinhiringisbecomingwidespread.Asurveyb
流行性感冒的确诊的主要依据是A、发病季节 B、呼吸道症状轻微而全身中毒症状重
下述不是大量心包积液X线主要表现的是A.心弓切迹消失 B.上腔静脉增宽 C.
建设工程项目总承包模式下,由承包人完成的工作是()。A.编制项目可行性研究报
某工程1993年签合同时,1994年相对于1993年的材料综合物价指数为110%
当归的功效是A.补血,止血,止痛,止泻 B.补血,止血,止痛,润肠 C.补血
共用题干 EveryDogHasHisSayKimikoFukuda
最新回复
(
0
)