The project schedule is more than a docu

练习题库2022-08-02  75

问题 The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to(  ).A.measure, delay, record, distribute, analyze, and directB.plan, schedule, monitor, control, report, and forecastC.promote, highlight, monitor, control, forecast, and reportD.emphasize, visualize, analyze, conceptualize, report, and record

选项 A.measure, delay, record, distribute, analyze, and direct
B.plan, schedule, monitor, control, report, and forecast
C.promote, highlight, monitor, control, forecast, and report
D.emphasize, visualize, analyze, conceptualize, report, and record

答案 B

解析 项目计划包括了多个文件,规定了在一段时间内的活动,代表该项目的时间进度,它是一种管理工具,用于决策。因此,项目管理团队使用进度计划于
A、措施、延迟、记录、分发、分析、直接
B、方案、计划、监测、控制、报表、预测
C、促进、突显、监测、控制、预测,报表
D、强调、可视化、分析、概念化、报表、记录