he Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ().A.Change control boardB.Project management officeC.Project managerD.Configuration management officer
选项
答案
C
解析
项目整体变更控制流程贯穿于项目开始到项目完成的各阶段,并且最终是()的职责。A.变更控制委员会B.项目管理办公室C.项目经理D.配置管理员
转载请注明原文地址:https://tihaiku.com/congyezige/2301720.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Workperformanceinformationiscirculat
ThePerformIntegratedChangeControlpr
ThePerformIntegratedChangeControl
ThePerformIntegratedChangeControl
PerformQualityControlistheprocesso
TheperformIntegratedChangeContorlpr
Youhavejusttakencontrolofaproject
Changesmayberequestedbyanystakehol
Iftheapprovedchangerequestshavean
Yourhavejusttakencontrolofaprojec
随机试题
IfIhadremembered______thewindow,thethiefwouldnothavegotin.A、toclose
Peoplebornintheautumnlivelongerthanthoseborninthespring.Andthe
Accordingtotheauthor,theAncientGreeksandRomans______.[br]TheGreeksa
地下通信管道用塑料管按成型外观划分硬直管、硬弯管、可挠管。()
(2012年)建筑沉降观测中,确定观测点布设位置,应重点考虑的是()。
2012年末,中国大陆总人口135404万人,全年出生人口1635万人,死亡人口
高危险区域内使用的消防应急照明和疏散指示系统,其应急转换时间不应大于()s。A.
下列指标是衡量货币市场基金风险的有()。A:投资组合平均剩余期限 B:融资比例
银行业消费者的主要权利有( )。A.安全权 B.监督权 C.受教育权 D
不符合高强度螺栓连接的要求有( )A.高强度螺栓连接处的摩擦面,采用手工砂轮打磨
最新回复
(
0
)