he Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ().A.Change control boardB.Project management officeC.Project managerD.Configuration management officer
选项
答案
C
解析
项目整体变更控制流程贯穿于项目开始到项目完成的各阶段,并且最终是()的职责。A.变更控制委员会B.项目管理办公室C.项目经理D.配置管理员
转载请注明原文地址:https://tihaiku.com/congyezige/2301720.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Workperformanceinformationiscirculat
ThePerformIntegratedChangeControlpr
ThePerformIntegratedChangeControl
ThePerformIntegratedChangeControl
PerformQualityControlistheprocesso
TheperformIntegratedChangeContorlpr
Youhavejusttakencontrolofaproject
Changesmayberequestedbyanystakehol
Iftheapprovedchangerequestshavean
Yourhavejusttakencontrolofaprojec
随机试题
Whichdoyouthinkis_______important,moneyorhealth?A、moreB、mostC、theA本题
Ourgoalistocreateatransportationservicethatofferscustomersacompetiti
Overthelastdecadetherehasbeenincreasinginterestinnewertechniques
Theinnervoiceofpeoplewhoappearunconsciouscannowbeheard.Forthef
[originaltext]M:[9]TheRepublicanPartyinAmericaisopposingstemcellresear
[originaltext]MymotherwasborninasmalltowninnorthernItaly.[16]She
甲公司是汽车制造企业,近年来新能源汽车产业及市场迅猛增长。为了适应市场需求,拟进
测试的时间过长,容易引起被试者的疲劳和反感,影响测试结果的稳定性和( )。A.
下列不属于腺淋巴瘤上皮细胞成分的是A.高柱状上皮细胞 B.立方状基底细胞 C
道路运输合同是以道路运输企业或个人作为承运人的运输合同,运输合同的客体为()。
最新回复
(
0
)