问题 Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (  ).A.executive IT manager B.project mangerC.change control board D.project sponsor

选项 A.executive IT manager
B.project manger
C.change control board
D.project sponsor

答案 C

解析 项目变更可以由IT经理executiveITmanager、项目管理者projectmanager、项目发起人projectsponsor等任意项目干系人发起,但只有变更控制委员会changecontrolboard才能授权批准变更,所以选C。