If the approved change requests have an effect on the project scope,then the corresponding component documents and cost baselines,and( )of the project management plan are revised and reissued to reflect the approved changes.A.developing baselines B.testing baselines C.schedule base lines D.ending baselines
选项
A.developing baselines
B.testing baselines
C.schedule base lines
D.ending baselines
答案
C
解析
如果批准的变更请求对项目范围的影响,那么相应的组件文件和成本基线,和进度基线的项目管理计划。修订再版反映批准的变更。(75) A.发展基线 B.测试基线 C.进度基线 D.结束基线
转载请注明原文地址:https://tihaiku.com/congyezige/2296001.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )istheapprovedversionofthetime-
ThePerformIntegratedChangeControlpr
hePerformIntegratedChangeControlpro
ThePerformIntegratedChangeControl
ThePerformIntegratedChangeControl
TheperformIntegratedChangeContorlpr
Iftheapprovedchangerequestshavean
Changesmayberequestedbyanystakehol
Iftheapprovedchangerequestshavean
Changesmayberequestedbyanystakehol
随机试题
LanguageandHumanityLanguageispowerfulanditcanhe
BornonJuly31,1965,inGloucestershire,England,JoanneKathleenRowling
Thepredictabilityofourmortalityratesissomethingthathaslongpuzzled
WhichofthefollowingpartiesisNOTBritish?A、ConservativeParty.B、LabourPar
Ionlyknowthemanby______butIhaveneverspokentohim.A、chanceB、heartC、si
AloeVitaminHandCreamArichyetlightweightnon-greasytexturethata
充气连接管路的接口安装在报警阀气室充注水位以上部位,充气连接管道的直径不得小于(
根据施工用电的重要性和停电造成的损失程度,将施工用电分为()类负荷。A、2 B
2020年1-12月份,全市固定资产投资3815.36亿元,同比增长6.1%。房
养阴清肺汤的君药是( )。A.生地 B.麦冬 C.玄参 D.白芍
最新回复
(
0
)