Perform Quality Control is the process of monitoring and recording results*of executing the Quality Plan activities to assess performance and recommend necessary changes.() are the techniques and tools in performing quality control① Statistical sampling ② Run chart③ Control charts ④ Critical Path Method⑤ Pareto chart⑥ Cause and effect diagramsA.①②③④B.②③④⑤C.①②③⑤⑥D.①③④⑤⑥
选项
A.①②③④
B.②③④⑤
C.①②③⑤⑥
D.①③④⑤⑥
答案
C
解析
实现项目质量控制的方法、技术和工具包括统计抽样(Statistical sampling)、运行图 (Run chart)、控制图(Control charts)、帕累托图(Pareto chart),以及因果图(Cause and effect diagrams)等。关键路径法(Critical Path Method)是制定项目进度计划的方法,因此选C。
转载请注明原文地址:https://tihaiku.com/congyezige/2299700.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thehighestlevelofqualitymanagement
( )isaprocessofdevelopingadocumen
Workperformanceinformationiscirculat
( )istheprocessofimplementingrisk
( )isaprocessofdevelopingadetail
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
( )istheoutputofthequalityplannin
PlanQualityistheprocessofidentifyi
PerformQualityControlistheprocesso
随机试题
Peopledonothavesecrettrolleysatthesupermarket,sohowcanitbeaviol
男性,48岁,反复水肿伴血压高10年,近半年夜尿增多,有时牙龈出血、气促,Hb
在车行道下埋设燃气管道的最小深度应为( )。A.0.5m B.0.6m C
能够从上述资料中推出的是:A.2010—2011年我国外商投资企业进出口
有关可待因的说法正确的是A.外周性镇咳药B.兼有镇痛作用的镇咳药C.非成瘾性镇咳
无自然采光的楼梯间、封闭楼梯间、防烟楼梯间及其前室的顶棚、墙面和地面均应采用(
下列属于市场风险报告补充信息的是( )。A.模型局限性 B.模型运行结果
用自己的话来表达问题的结构,从而形成解决问题的路径是指()。 A.形成问题的表
急性根尖周脓肿时,医生建立最佳的引流通道是A.根尖孔-根管-龋洞 B.根尖部-
下列各项,不允许投标人自主报价的有( )。A.单价措施项目费 B.安全文明施
最新回复
(
0
)