问题
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ).A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer
选项
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
答案
C
解析
整体变更控制过程的实施从项目开始到结束一直进行。这是(项目经理PM)的最终责任。
A.变更控制委员会CCB
B.项目管理办公室PMO
C.项目经理PM
D.配置管理专员CMO
转载请注明原文地址:https://tihaiku.com/congyezige/2302919.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Workperformanceinformationiscirculat
( )seektoperformrootcauseinvestiga
ThePerformIntegratedChangeControlpr
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
hePerformIntegratedChangeControlpro
ThePerformIntegratedChangeControl
Youhavejusttakencontrolofaproject
Changesmayberequestedbyanystakehol
Iftheapprovedchangerequestshavean
Yourhavejusttakencontrolofaprojec
随机试题
【B1】[br]【B2】A、livedB、enjoyedC、spendC从语意上来看应为度过他的童年因此选spent。
Accordingtoconservationists,whydoestheInteractposeathreattoendangered
SomeAdvicetoCollegeGraduatesI.Adviceonyourdreams
IsItCheapertoBeaWoman—oraMan?A)Tocelebratethelau
在下述黏膜组织中,何处无黏膜下层A.龈 B.唇 C.舌腹 D.口底 E.
下列哪项是月经先期肝郁血热证的主症A.经量增多 B.经量减少 C.经量或多或
小王持有某银行的信用卡,他近期内打算出国旅游,于是向该银行电话申请调高临时信用额
不属于外源性感染的是( )。A.病原体来源于工作人员污染的手 B.病原体来源
关于水体自净的说法错误的是:A.无氧状态时水体生物自净功能减弱 B.水体自
男,15岁。冬季一天清晨,同学发现其人事不省,室内煤炉取暖,门窗紧闭。送来急诊时
最新回复
(
0
)