首页
登录
从业资格
The Perform Integrated Change Control pr
The Perform Integrated Change Control pr
题库
2022-08-02
44
问题
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ).A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer
选项
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
答案
C
解析
整体变更控制过程的实施从项目开始到结束一直进行。这是(项目经理PM)的最终责任。
A.变更控制委员会CCB
B.项目管理办公室PMO
C.项目经理PM
D.配置管理专员CMO
转载请注明原文地址:https://tihaiku.com/congyezige/2302919.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Workperformanceinformationiscirculat
( )seektoperformrootcauseinvestiga
ThePerformIntegratedChangeControlpr
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
hePerformIntegratedChangeControlpro
ThePerformIntegratedChangeControl
Youhavejusttakencontrolofaproject
Changesmayberequestedbyanystakehol
Iftheapprovedchangerequestshavean
Yourhavejusttakencontrolofaprojec
随机试题
SavingfortheFuture-Purposeofsaving1.Womensa
Recentyearshavebroughtminority-ownedbusinessesintheUnitedStatesunp
[originaltext]M:Let’slookatyourproblem:youalwaysfailthejobinterviews
[originaltext]W:Hi,ProfessorHiggins.M:Hi,Julia.W:Wouldyoubeabletoh
坚果是以种仁为食用部分,下列品种属于坚果的是( )。A.腰果 B.杏干 C
八脉交会穴中,主治心、胸、胃部疾患的是A.外关、足临泣 B.列缺、照海 C.
假设检验的类别( ) Ⅰ.同侧检验 Ⅱ.多侧检验 Ⅲ.参数假设检验 Ⅳ
气逆导致吐血的生理学基础是A.气能生血 B.气能行血 C.气能摄血 D.血
商业银行贷后管理中有关经营者的预警信号主要包括()。A.冒险投资于其他新业务
国际工程投标前,对于生产要素询价主要包括的内容有()。A、当地的生活费用指数、
最新回复
(
0
)