You have just taken control of a project
You have just taken control of a project
题库
2022-08-02
70
问题
You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information.A、Resource assignment matrix B、Change control planC、Project charter D、Client organization chart
选项
A、Resource assignment matrix
B、Change control plan
C、Project charter
D、Client organization chart
答案
B
解析
在项目执行的过程中你刚刚获得项目的控制权利,并且需要了解谁具有范围修正的权限,什么文件提供了该信息。
A.资源分配矩阵
B.变更控制计划
C.项目章程
D.客户的组织结构图
转载请注明原文地址:https://tihaiku.com/congyezige/2297223.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojectmanagementandsystemsengine
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
Establishingaproject( )involveslis
Inprojectmanagement,a( )isalisto
Theprojectbudgethasbeenfinalized.Ad
随机试题
Myjobwastomakeclassroomobservationsandencourageatrainingprogramt
Crimeisincreasingworldwide.Thereiseveryreasontobelievethe(1)_____
[originaltext]M:Goodmorning.W:Goodmorning.HowcanIhelpyou?M:Iunders
Fortheaverageperson,weallstartofwithapproximatelythesame(1)_____
设S是一个长度为n的非空字符串,其中的字符各不相同,则其互异的非平凡子串
各种运输方式内外部的各个方面的构成和联系,就是( )。 A.运输系统
依据《企业职工伤亡事故分类》(GB6441),下列事故中,属于物体打击事故类别
在建筑构造的环境影响因素中,属于自然因素的是( )。A.火灾 B.噪声 C
下列各项,属于期间费用内容的是()。 A.变动费用 B.固定费用
根据《注册建行师执业管理办法(试行)》,注册建造师不得同时担任两个及以上建设工程
最新回复
(
0
)