The Perform Integrated Change Control
The Perform Integrated Change Control
考试题库
2022-08-02
57
问题
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer
选项
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
答案
C
解析
实施整体变更控制过程是从项目开始到项目结束并且是项目经理的最终责任。
转载请注明原文地址:https://tihaiku.com/congyezige/2299717.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isameasureofscheduleperformance
Workperformanceinformationiscirculat
( )seektoperformrootcauseinvestiga
PerformQualityControlistheprocesso
hePerformIntegratedChangeControlpro
( )seekstoperformrootcauseinvestig
Youhavejusttakencontrolofaproject
Iftheapprovedchangerequestshavean
Changesmayberequestedbyanystakehol
Manyoftheactivitiesperformedduring
随机试题
[originaltext]M:EnglishLanguageCenter.MayIhelpyou?W:Yes.I’mcallingt
Dr.RablenandDr.OswaldhavejustpublishedastudywhichconcludesthatN
Inthepast,Americanfamiliestendedtobe[br][originaltext]Inthepast,
满足下列哪个条件,可直接采用四格表检验的基本公式或专用公式而无需校正A.n≥40
Afteracceptanceandformaltransferof
通过现况调查可得出A.死亡率 B.罹患率 C.患病率 D.发病率 E.病
根据《合同法》的规定,有效的合同转让将使相关权利随之转移,但()除外。A
把下面的六个图形分为两类,使每一类图形都有各自的共同特征或规律,分类正确的一项是
疾病初期,恶寒与发热同时并见,应属A.表寒里热证 B.里热证 C.外感表证
下列剂型作用速度最快的是A.舌下给药 B.口服液体制剂 C.静脉注射 D.
最新回复
(
0
)