The Perform Integrated Change Control
The Perform Integrated Change Control
考试题库
2022-08-02
35
问题
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer
选项
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
答案
C
解析
实施整体变更控制过程是从项目开始到项目结束并且是项目经理的最终责任。
转载请注明原文地址:https://tihaiku.com/congyezige/2299717.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isameasureofscheduleperformance
Workperformanceinformationiscirculat
( )seektoperformrootcauseinvestiga
PerformQualityControlistheprocesso
hePerformIntegratedChangeControlpro
( )seekstoperformrootcauseinvestig
Youhavejusttakencontrolofaproject
Iftheapprovedchangerequestshavean
Changesmayberequestedbyanystakehol
Manyoftheactivitiesperformedduring
随机试题
Overseasassignmentsarebecomingincreasinglyimportanttoadvancementwith
Chancesofgettingthejobwereslim,sotheyoungmanfelt______aboutthefutur
A.绝对变性反应 B.部分变性反应 C.无明显变化 D.无变性反应 E.
完全竞争市场中,厂商产品所对应的价格是( )。A.没有政府干预的市场价格 B
简述幼儿感知觉发展的主要阶段。
根据《基础地理信息档案管理与保护规范》,下列关于成果归档的说法中,正确的是()
我国对于货物的强制性质量监督手段包括工业产品生产许可制度和()。A.强制性产品
(2017年真题)国债期货合约是一种()。A.利率风险管理工具 B.汇率
肿瘤化疗的主要不良反应是A.口腔溃疡 B.胃肠道反应 C.骨髓抑制 D.脱
某项目总投资为2000万元,其中债务资金为500万元,项目运营期内年平均净利润为
最新回复
(
0
)