首页
登录
从业资格
The()provides the project manager with t
The()provides the project manager with t
最全题库
2022-08-02
69
问题
The()provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.contractC.project human resource planD.project charter
选项
A.project management plan
B.contract
C.project human resource plan
D.project charter
答案
D
解析
项目章程为项目经理使用组织资源进行项目活动提供了授权。 A.项目管理计划 B.合同 C.项目人力资源计划 D.项目章程
转载请注明原文地址:https://tihaiku.com/congyezige/2301722.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
( )isaprojectmanagementtechniquefo
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectscheduleismorethanadocu
随机试题
OurculturehascausedmostAmericanstoassumenotonlythatourlanguagei
Britain’seastmidlandswereoncethepictureofEnglishcountryside,alive
Ifadultslikedtoreadbooksthatwereexceedinglydifficult,they’dallbe
下列有关安全使用家用电器的说法中,错误的是()。A.电冰箱及电视机等电器不要短
产妇,37岁,GP,胎膜已破3天,临产2天,胎动消失半天,由乡卫生院转来。体检:
当下卧地层具有明显横向坡度时,应从下(),并在低侧边部多抛投不少于2米宽,形
A.祛风通络,清热泻火 B.祛风通络,强筋骨 C.舒筋通络,化湿和胃 D.
关于房地产投资项目敏感性分析的说法,正确的有( )。A.敏感性分析是一种动态不确
恒牙建立初期一个重要的决定因素是A.建的动力平衡 B.种族 C.遗传 D.
根据行政处罚法的规定,下列表述正确的有()。A.行政处罚的实施机关、立案依据、
最新回复
(
0
)