To ensure the project team provides the functionality the customer expects in a new piece of software, the project manager ask the customer for sign-off on the design criteria. These documents are( ).A.technical specificationsB.performance specificationsC.product descriptionsD.quality assurance
选项
A.technical specifications
B.performance specifications
C.product descriptions
D.quality assurance
答案
A
解析
为了确保项目团队提供在新软件中顾客所期望的功能,项目经理请求顾客在设计标准上签字确认。这些文档是(技术规格说明书 )。
A、技术规格说明书 B、性能规格说明书 C、产品描述 D、质量保证
转载请注明原文地址:https://tihaiku.com/congyezige/2302927.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Qualitymanagementensuresthatanorgan
Inprojectmanagementandsystemsengine
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Ascheduleiscommonlyusedinprojectp
Establishingaproject( )involveslis
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
Readersareinvitedto_________theiropinionsonanyoftheissuesdiscussedh
Therewasatimewhencollegewasaplacewhereyoungadultscouldexpandth
Inoneoftheexercises,theprofessoraskedhisstudentto[br][originaltext]
[originaltext]W:MikeandIarehavingapartynextweek.Wewonderifyouand
夜间起步前,应当先开启近光灯。()
一项新的国家标准出台,某项目经理意识到新标准中的某些规定将导致其目前负责的一个项
流行病学是研究疾病、健康状态和事件在人群中的()因素,用以预防和控制疾病,促进健
下列描述中不属于外币有价证券的是:A、政府债券 B、股票 C、票据 D、公
以下不由借款人为其申请个人旅游消费贷款的是()。A.借款申请人的兄弟
根据《建设工程项目管理规范>GB/T50326-2006,项目管理目标责任书由(
最新回复
(
0
)