The Project Management Triangle is a model of the constraints of project management. These constraints have been listed as scope(or quality),( ), and cost.A.resourceB.timeC.planD.tool
选项
A.resource
B.time
C.plan
D.tool
答案
B
解析
项目管理三角形是一种项目管理约束条件的模型。这些约束条件包含范围(或质量),(时间)和成本。
A.资源
B.时间
C.计划
D.工具
转载请注明原文地址:https://tihaiku.com/congyezige/2302548.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thehighestlevelofqualitymanagement
Qualitymanagementensuresthatanorgan
Configurationmanagementisfocusedont
Inaprojectplan,whentheprojectmana
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
( )managementincludesnegotiatingthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
随机试题
[originaltext]W:GoodMorning,thisisTGC!M:Goodmorning,WalterBarryhere,
Whatisthenewsmainlyabout?[br][originaltext]Threedaysofcommemora
ThepopulationinHongKongis______Chinese.A、popularlyB、predominantlyC、common
Thepassageconveysthemessagethatthewayforacompanytokeepoutoffinanc
经保存1周的全血,其主要有效成分是( )。A.红细胞、白细胞和稳定的凝血因子
下列属于刑事诉讼中强制措施的是()。A.警告 B.责令停止 C.逮捕
节能环保、新一代信息技术、生物、高端装备制造产业应属于()。A:支柱产业 B:
我国台湾地区的著名房地产经纪机构——信义房屋,在台湾率先创立了(),并在实际
A.3~6g B.5~10g C.3~5g D.3~10g E.3~9g
下列财产中不得抵押的有()。A.土地所有权 B.抵押人依法有权处置的国有机器
最新回复
(
0
)