The Project Management Triangle is a model of the constraints of project management. These constraints have been listed as scope(or quality),( ), and cost.A.resourceB.timeC.planD.tool
选项
A.resource
B.time
C.plan
D.tool
答案
B
解析
项目管理三角形是一种项目管理约束条件的模型。这些约束条件包含范围(或质量),(时间)和成本。
A.资源
B.时间
C.计划
D.工具
转载请注明原文地址:https://tihaiku.com/congyezige/2302548.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thehighestlevelofqualitymanagement
Qualitymanagementensuresthatanorgan
Configurationmanagementisfocusedont
Inaprojectplan,whentheprojectmana
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
( )managementincludesnegotiatingthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
随机试题
•Youwillhearabusinesspresentationaboutacceptingresponsibilityforsales
Whyarethebeescalled"AfricanizedHoneyBees"?[originaltext]Thesearethe
Foralltheirgreatdiversityofshapesandsizes,glacierscanbedivided
StudiesoftheWeddellsealinthelaboratoryhavedescribedthephysiologic
Owningamobilephonedefinitelymakeslifemoreconvenient,butyou’dbetterlim
氧化锌避雷器具有以下优点()。A.耐污性能好 B.有续流 C.能制成轻载避雷
某一110kv线路的接地距离保护的,零序补偿系数由0.667被误整为2,将使
个人理财业务是经()批准的一些用户中间业务。A.中国人民银行 B.中
项目是为了实现一个独特的目的而进行的()任务。A.长期性 B.明确性 C.临
公称直径300mm的阀门强度试验持续时间为()。A.15s B.30s C
最新回复
(
0
)