问题
The Project Management Triangle is a model of the constraints of project management. These constraints have been listed as scope(or quality),( ), and cost.A.resourceB.timeC.planD.tool
选项
A.resource
B.time
C.plan
D.tool
答案
B
解析
项目管理三角形是一种项目管理约束条件的模型。这些约束条件包含范围(或质量),(时间)和成本。
A.资源
B.时间
C.计划
D.工具
转载请注明原文地址:https://tihaiku.com/congyezige/2302548.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thehighestlevelofqualitymanagement
Qualitymanagementensuresthatanorgan
Configurationmanagementisfocusedont
Inaprojectplan,whentheprojectmana
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
( )managementincludesnegotiatingthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
随机试题
Therewasaheavyfogthismorning,sonoplanecould______ontime.A、getthrou
Thirty-twopeoplewatchedkittyGenovesebeingkilledrightbeneaththeirwin
Unlessmeasuresaretakenatonce,thereisapossibilitythatalltheocean
Whatwasthewheatproductionlastyear?[br][originaltext]Wheatsupplies
TheInternetbeganinthe1960sasasmallnetworkofacademicandgovernmen
一固体壁面与流体相接触,内部的温度变化遵循热传导方程,其边界条件为( )。
患者,女,45岁。2天前感觉胁肋部皮肤灼热疼痛,皮色发红,继则出现簇集性粟粒状疱
(一)某投资者购买了一间建筑面积为100m2的店铺用于出租经营,购买价格为1
态度的结构包括()。A.能力 B.认知 C.情感 D.本能 E.行为
下列选项中,关于印花税特点的说法中错误的是( )。A.兼有凭证税和行为税性质
最新回复
(
0
)