Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.A.cost management planB.risk management planC.scope management planD.management schedule
选项
A.cost management plan
B.risk management plan
C.scope management plan
D.management schedule
答案
D
解析
建立一个项目(进度管理计划)包含列出里程碑、活动和可交付的计划起止日期,其中要考虑到员工的安排的因素。
A.成本管理计划
B.风险管理计划
C.范围管理计划
D.进度管理计划
转载请注明原文地址:https://tihaiku.com/congyezige/2302550.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Inprojectmanagementandsystemsengine
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Inprojectmanagement,a( )isalisto
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
随机试题
WhendidMichaeldecidetobecomechildless?[br][originaltext]Inthepas
[originaltext]Mostyoungwomenbelievetheywillachieveabalancebetweena
AnortherncoldspellgrippedmuchofnorthernandeasternChinayesterday,a
中国香烟占全球香烟的三分之一,每年因吸烟而死亡的人数超过100万人。2015年6月,北京实施“史上最严”的控烟条例,除了所有公共场所、工作场所室内区域及
PreparingforChina’sUrbanBillionThescaleandpaceofChina’surbanizatio
根据货币时间价值概念,下列不属于货币终值影响因素的是( )。A.计息的方法 B
()模式的特点是建立在科学管理的基础上,即事先必须制定物料消耗定额,然后编制
根据《环境保护法》,重点排污单位应当按照国家有关规定和监测规范( )。A.安装
普通低合金钢比碳素结构钢具有()。A.较高的韧性 B.良好的焊接性能 C.
下列成分为C3转化酶的是A.C1s B.C234 C.C3bBb D.C3
最新回复
(
0
)