A schedule is commonly used in project planning and project portfolio management. ( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.A.EssencesB.ElementsC.PurposesD.Issues
选项
A.Essences
B.Elements
C.Purposes
D.Issues
答案
B
解析
时间表(计划表)在项目规划和项目组合管理中使用广泛。 时间表上的(元素)可能与工作分解结构(WBS)的终端元素,工作说明书,或合同数据需求清单等密切相关。
A.精华
B.元素
C.用途
D.问题
转载请注明原文地址:https://tihaiku.com/congyezige/2302923.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Inprojecttimemanagement,activitydef
Inprojectmanagementandsystemsengine
ProjectIntegrationManagementincludes
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Establishingaproject( )involveslis
WhichofthefollowingProjectScopeMan
Aprojectmanageriscalledtoaninform
Theprojectscheduleismorethanadocu
随机试题
[originaltext]MostAmericanuniversitystudentsstudyfor4yearsormoret
设计概算审查的方法主要有( )。A.对比分析法 B.查询核实法 C.联合会
“正确舆论”的含义通常应当包括()A.投公众所好 B.凡宣传皆好事 C.公
改良Heller术的手术要点不包括A.切断食管下段一侧所有环行肌纤维 B.贲门
患者男,65岁。反复咳嗽,咳痰15年,活动后气短2年,双下肢水肿1个月。本次入院
A.晚上7~8时一次给药 B.餐后2~3小时内给药 C.早晨7~8时一次给药
简述现代企业人力资源管理各个历史发展阶段的特点。
布地奈德口服给药的效能约为皮质醇的A.15倍 B.25倍 C.40倍 D.
APC递呈外源性Ag的正确描述是A.外源性Ag可在局部或局部引流至淋巴组织接触A
(2017年真题)甲公司大修期间,委托乙公司维修车间车床,委托丙公司维护同一车间
最新回复
(
0
)