Project work packages are typicallydecomposed into smaller components called activities to provide a basis for ( ) , scheduling, executing, andmonitoring and controlling the project work.A.reviewing B.estimating C.auditing D.expecting
选项
A.reviewing
B.estimating
C.auditing
D.expecting
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2295956.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
随机试题
Allofthetechnologicaladvancesthathaveincreasedthequalityofmusich
MarcoPolowasborninItalyin1254.Hewasthemost【71】f______westernerto
ManyFuropeanuniversities,meanwhile,arestillmostlydependentongovernmen
Ihearmanyparentscomplainingtheirteenagechildrenarerebelling.Iwish
Eachandeveryoneofusisresponsibleforthegreenhousegaseswesendin
若用8位机器码表示十进制-101,则原码表示形式为();补码表示的形式为()。A
最佳过敏反应诊断方法是A.点刺试验B.血清总IgE测定C.血清特异性IgE测定D
下列属于平衡计分卡中客户方面绩效指标的是()。A.经济增加值 B.品牌市场价
根据《中华人民共和国环境影响评价法》,国务院有关部门、设区的市级以上人民政府及其
8个月婴儿,因腹泻脱水,测血钠135mmol/L,最适宜补充累积丢失的液体是
最新回复
(
0
)