首页
登录
从业资格
Project work packages are typically dec
Project work packages are typically dec
题库
2022-08-02
52
问题
Project work packages are typicallydecomposed into smaller components called activities to provide a basis for ( ) , scheduling, executing, andmonitoring and controlling the project work.A.reviewing B.estimating C.auditing D.expecting
选项
A.reviewing
B.estimating
C.auditing
D.expecting
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2295956.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
随机试题
ThemoreIreflectonthe23impressiveyearssincethesigningoftheMontr
Technologiescollapsethedistancebetweenadesireanditsfulfillmentby
Trillionsofincrediblytinydiamonds,possiblyformedbyadyingstarbefo
FromGolda:theLifeofIsrael’sPrimeMinisterTheStrug
[originaltext]DeepSpringsisanAmericancollege.Itisanunusualcollege
Goodevening,everyone.AsmanyofyouknowIoftentravelformyjobas
风湿热诊断标准中的主要表现不包括A、舞蹈病 B、关节痛 C、心肌炎 D、皮
责令改正不是统计法律责任的一种形式。()
城市陆上消防站责任区面积不宜大于7平方公里,主要是考虑下列哪项因素?()(
下列有关垫资的说法中,正确的有( )。A.当事人对垫资和垫资利息有约定,承包人可
最新回复
(
0
)