Project work packages are typicallydecomposed into smaller components called activities to provide a basis for ( ) , scheduling, executing, andmonitoring and controlling the project work.A.reviewing B.estimating C.auditing D.expecting
选项
A.reviewing
B.estimating
C.auditing
D.expecting
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2295956.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
随机试题
Fatherdidn’ttellmewhenhe_______.I’11telephoneyouassoonashe_______.A
WorkisaveryimportantpartoflifeintheUnitedStates.WhentheearlyP
Somedeviantusesoftechnologyarecriminal,thoughnotallparticipantss
对信访事项有权处理的行政机关,对信访事项必须(),按照法律、法规、规章等规定,
若进度偏差大于总时差,说明此偏差对总工期无影响,但它对后续工作的影响程度,需要根
脑受损后,设置训练程序的依据错误的是A.正常运动发育延迟或发育不完善 B.治疗
男性,16岁。食蚕豆后突然畏寒,发热,皮肤发黄。血红蛋白70g/L,网织红细胞0
论述重症胰腺炎的并发症
中医治疗疾病主要着眼于A.症状 B.主诉 C.证候 D.疾病 E.体征
一个14个月的孩子被成人抱着时,着急地往柜子的方向挣扎,嘴里叫“ta,to”(音
最新回复
(
0
)