A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.A.EssencesB.ElementsC.PurposesD.Issues
选项
A.Essences
B.Elements
C.Purposes
D.Issues
答案
B
解析
时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构(WBS)的最终元素,工作说明书,或合同数据需求清单密切相关。
转载请注明原文地址:https://tihaiku.com/congyezige/2299720.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inprojectmanagementandsystemsengine
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
如果在一个课程注册系统中,定义了类CourseSchedule和类Course,
WhichofthefollowingProjectScopeMan
Aprojectmanageriscalledtoaninform
Theprojectscheduleismorethanadocu
随机试题
[originaltext]下面你将听到的是一段有关国际局势的讲话。InthewakeoftheColdWar,theworldh
[originaltext]W:WhatdoyouwantfromtheWoolworth,Mark?M:Oh,Ijustneed
下肢伸面高出皮面散在出血性丘疹A.风湿热 B.川崎病 C.系统性红斑狼疮
LOF基金份额的场内赎回申报单位为()。A.100份或其整数倍 B.5
A.20℃B.40℃C.35℃D.15℃E.10℃防虫的关键温度是
属于可见配伍变化的是A.效价下降 B.水解反应 C.升华 D.结晶 E.
1/2+(1/2)2+(1/2)3+(1/2)4的值是()。 A.1/16
妇女社会工作主要是以妇女为服务对象的社会工作,其工作内容涉及面很广。以下针对全体
按照国家现行规定,建设项目根据资金性质、环境影响、社会影响等因素的不同,其审批程
银行承兑汇票的承兑银行,应当按照票面金额向出票人收取()的手续费。A:千分之一
最新回复
(
0
)