问题
A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.A.EssencesB.ElementsC.PurposesD.Issues
选项
A.Essences
B.Elements
C.Purposes
D.Issues
答案
B
解析
时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构(WBS)的最终元素,工作说明书,或合同数据需求清单密切相关。
转载请注明原文地址:https://tihaiku.com/congyezige/2299720.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inprojectmanagementandsystemsengine
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
如果在一个课程注册系统中,定义了类CourseSchedule和类Course,
WhichofthefollowingProjectScopeMan
Aprojectmanageriscalledtoaninform
Theprojectscheduleismorethanadocu
随机试题
Feministcriticshavelongdebatedtheextenttowhichgenderplays
[originaltext]M:IamreallygettingworriedaboutMary.She.willsitinfora
[originaltext]Haveyouevertraveledonanyofthegiantjetairplanes?If
水加热器前端应留有抽出加热盘管的位置,一侧通道净宽为()m。A.0.6 B
女性,48岁,月经紊乱1年,偶感潮热、出汗,现阴道出血20余天。既往月经规律5~
寒性哮喘的首选方剂是A.三拗汤 B.二陈汤 C.小青龙汤 D.定喘汤 E
心下痞,但满而不痛,或呕吐,肠鸣下利,舌苔腻而微黄应选用的方剂是A.葛根黄芩黄连
下列有关IgE测定方法,错误的是A.RIAB.CLIAC.ELISAD.PCRE
在一定期间及特定的业务量范围内,关于成本与业务量关系,下列说法正确的有()。A.
根据《规划环境影响评价技术导则—总纲》,规划环境影响评价的目的表述正确的是(
最新回复
(
0
)