The () technique involves using project characteristics in a mathematical modelto predict total project costs. Models can be simple or complex.A.Cost Aggregation B.Reserve Analysis C.ParametriC.Estimating D.Funding Limit Reconciliation
选项
A.Cost Aggregation
B.Reserve Analysis
C.ParametriC.Estimating
D.Funding Limit Reconciliation
答案
C
解析
参数估算涉及在一个数学模型中利用项目特性来预测整体项目成本,模拟可以是简单的也可以是复杂的。
转载请注明原文地址:https://tihaiku.com/congyezige/2295945.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Inprojecttimemanagement,activitydef
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Theprojectbudgethasbeenfinalized.Ad
Theprojectscheduleismorethanadocu
Theearnedvaluetechniqueisacommonly
随机试题
"Pain,"asAlbertSchweitzeroncesaid,"isamoreterriblelordofmankind
WhatisthespecialfeatureoftheGoldenRice?[br][originaltext](7)"Gol
Thatanecologicalcrisisconfrontshumankindisnowsocentraltoourthink
Historianstendtotellthesamejokewhentheyaredescribinghistoryeduca
Athirdoftheplanet’slandisseverelydegradedandfertilesoilisbeing
Thedemonstrationisto[originaltext]Onthesecondanniversaryoftheoverth
LudwigvanBeethovenwasoneofthegreatest【B1】______whoeverlived.Hethoug
治疗寒湿凝滞之痛经,首选方剂为A、膈下逐瘀汤 B、少腹逐瘀汤 C、暖肝煎
精密、复杂器械的清洗和有机物污染较重器械的清洗步骤为A.冲洗、漂洗、洗涤、再冲洗
为了防范物业管理风险,物业服务企业需要通过()改进经营管理方式。A:机制创新
最新回复
(
0
)