首页
登录
从业资格
The earned value technique is a commonly
The earned value technique is a commonly
最全题库
2022-08-02
72
问题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
选项
A.the project is a head of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
答案
B
解析
挣值技术是一种综合了范围、成本、进度指标的绩效测量方法,帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着:(74)A.项目滞后B.项目超前C.项目超支D.成本有结余
转载请注明原文地址:https://tihaiku.com/congyezige/2299751.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
Ethernetisthecommonlyusedlocalarea
Earnedvaluemanagement(EVM)integrates
Earnedvaluemanagement(EvM)integrates
Aprojectmanagementtechniquethatisc
Ethernetisthecommonlyusedlocalarea
()isaprojectmangementtechniqueform
()isoneofthetoolsandtechniqueso
Earnedvaluemanagement(EVM)integrates
()isatechniqueforestimatingthedu
随机试题
Morepeopledieoftuberculosis(结核病)thanofanyotherdiseasecausedbyas
HowlongdoeshesurfontheInternetonschoolday?[originaltext]Interviewer:
TheoriesofHistoryI.Howmuchweknowabouthistory?
Scienceisadominantthemeinourculture.Sinceittouchesalmosteveryfa
在工程项目设计方案评价与优化过程中,最基本和最重要的工作内容是()。A:针对不
臂丛牵拉试验阳性常见于A.神经根型颈椎病病人 B.椎动脉型颈椎病病人 C.脊
Je3D4076有两台100kVA变压器并列运行,第一台变压器的短路电压为4%,
某社区的老年人向社会工作者反映,该社区周边的健身设施太少,难以满足娱乐锻炼的需要
(2019年真题)下列有关公司合并、分立规则的说法中,正确的有()。A.有限责
下列不属于金融工具的有( )。A.普通股股票 B.预付账款 C.债权投资
最新回复
(
0
)