首页
登录
从业资格
The earned value technique is a commonly
The earned value technique is a commonly
最全题库
2022-08-02
25
问题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
选项
A.the project is a head of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
答案
B
解析
挣值技术是一种综合了范围、成本、进度指标的绩效测量方法,帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着:(74)A.项目滞后B.项目超前C.项目超支D.成本有结余
转载请注明原文地址:https://tihaiku.com/congyezige/2299751.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
Ethernetisthecommonlyusedlocalarea
Earnedvaluemanagement(EVM)integrates
Earnedvaluemanagement(EvM)integrates
Aprojectmanagementtechniquethatisc
Ethernetisthecommonlyusedlocalarea
()isaprojectmangementtechniqueform
()isoneofthetoolsandtechniqueso
Earnedvaluemanagement(EVM)integrates
()isatechniqueforestimatingthedu
随机试题
A—CartoonCityB—SkyofArtsC—RoadtoHealth
TheUnitedStates’predominanceinscienceandtechnologyisfading,arepor
Fewgreatarchitectshavebeensoadamantintheirbeliefintheintegration
师带徒、现场技术指导、工作交底、绩效面谈均是一种机会式的培训。
设A为n阶方阵,B是A经过若干次初等行变换得到的矩阵,则下列结论正确的
评价薄荷油质量的指标性成分是A:薄荷酮B:醋酸薄荷酯C:桉叶素D:薄荷醇
对于个别运输需求来说,其在时间、空间上具有( )。 A.不特定性 B
《教育法》规定,明知校舍或者教育教学设施有危险,而不采取措施,造成人员伤亡或者重
2010-5.乙癸同源指的是 A.金水相生B.精血互化C.津气互生D.
根据《水利工程建设标准强制性条文》(2020年版),关于劳动安全的说法,正确的有
最新回复
(
0
)