( )estimating is a technique for estimat
( )estimating is a technique for estimat
admin
2022-08-02
47
问题
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.A.Parametric B.Analogous C.Three-point D.Expert judgment
选项
A.Parametric
B.Analogous
C.Three-point
D.Expert judgment
答案
B
解析
类比估计是一项使用类似的活动或项目的历史数据,来估计活动的时间或成本的技术。 (73) A.参数 B.类比 C.三点 D.专家判断
转载请注明原文地址:https://tihaiku.com/congyezige/2296017.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
()isaprojectmanagementtechniquefor
Thoseitemsareoftenestimatedinterms
Theearnedvaluetechniqueisacommonly
()isoneofthetoolsandtechniqueso
estimatingisatechniqueforestimating
allofthefollowingtoolsandtechnique
Manyusefultoolsandtechniquesareuse
()estimatingisatechniqueforestimat
Estimatingactivity durationsusesinfo
随机试题
Huntingwasoriginallyameansofprovidingfood,butithasnowbecomeasp
Executivepaychecksmightgrabthemostheadlines,butit’stop-tiermedical
ShotontheslyinGreecelastsummer,themovietalkedaboutCelineandJesse’s
(1)销售彩电取得不含税收入8600万元,与彩电配比的销售成本5660万
贮压式水基型灭火器的压力指示器标识为()。A.F B.S C.J D
A.筋痹 B.骨痹 C.肌痹 D.皮痹 E.脉痹以春遇此者为
以委托单为例,委托指令的基本要素包括()。A:买卖方向 B:价格 C:证券
适用优惠原产地规则的原产地证书,凡是受惠国政府指定机构签发的,即可适用于多批进口
麦克、汉斯与白文莉共同毕业于美国著名学府哈佛商学院职业经理人专业,麦克来自美国,
关于单层厂房屋架布置原则的说法,正确的有()。A.天窗上弦水平支撑一般设置
最新回复
(
0
)