首页
登录
从业资格
Estimating activity durations uses info
Estimating activity durations uses info
题库
2022-08-02
55
问题
Estimating activitydurations uses information on activity scope of ( ) , required resource types, estimatedresource quantities, and resource calendars.A.milestone B. baseline C.quality D. work
选项
A.milestone
B. baseline
C.quality
D. work
答案
D
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2295970.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
()isatechniqueforestimatingthedu
EstimateActivityDurationsistheproce
estimatingisatechniqueforestimating
()estimatingisatechniqueforestimat
Estimatingactivity durationsusesinfo
TheEstimateActivityResourceprocessi
Estimatingscheduleactivitycostsinvol
EstimateActivityDurationsistheprocessofe
随机试题
Wheredidthecustomergetthesweater?[originaltext]Allen:Excuseme.Couldyo
Theloudestoutcryaboutpovertyseemedtocomeinthewealthiestcountryby
HenryFord,thefamousU.S.inventorandcarmanufacturer,oncesaid,"Theb
Ifyou______hereforamoment,thebosswillcome.A、willwaitB、waitC、aregoi
BilltookadvantageofJean’s(eager)______topleaseeveryone.eagerness
截至2015年12月底,北京市文化及相关产业企业共有198948户,同比增长16
人在每一瞬间,将心理活动选择了某些对象而忽略了另一些对象。这一特点指的是注意的(
下列哪些说法体现了职权主义审判模式的特点?A.职权主义审判模式中,法官在审判程
使用比率分析法进行预测,如果这个大学预期明年注册的学生会增加1000名,则需要另
(2012年真题)下列关于车船税税率的表述中,正确的是( )。A.车船税实行定
最新回复
(
0
)