Estimating activity durations uses info

题库2022-08-02  31

问题 Estimating activitydurations uses information on activity scope of (  ) , required resource types, estimatedresource quantities, and resource calendars.A.milestone  B. baseline C.quality   D. work

选项 A.milestone
B. baseline
C.quality  
D. work

答案 D

解析
转载请注明原文地址:https://tihaiku.com/congyezige/2295970.html

最新回复(0)