( )is a project management technique for
( )is a project management technique for
资格题库
2022-08-02
67
问题
( )is a project management technique for measuring projectPerformance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.A.Critica1 path method(CPM)B.Earned value management(CEV)C.Net present value method(NPVM)D.Expert judgment method(EJM)
选项
A.Critica1 path method(CPM)
B.Earned value management(CEV)
C.Net present value method(NPVM)
D.Expert judgment method(EJM)
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2301744.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
Humanresourcemanagementisthemanagem
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
( )managementincludesnegotiatingthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
Establishingaproject( )involveslis
Riskmanagement's( )istoassureunce
随机试题
TaskTwo—SourcesoffundingForquestions18-22,matchtheextractswiththesou
Populationstendtogrowatanexponential(指数的)rate.Thismeansthatthey
[originaltext](JaneZhanghasanappointmentwithanacademicadvisortodiscus
WhywerethereprotestsinBritainagainstIran?[originaltext]TheBritish
露天爆破的警戒范围由()。A.爆破员确定 B.领导确定 C.爆破设计确定
《普通高中美术课程标准(实验)》中“课程性质”部分与“激发创新精神”搭配的短语是
已知M蛋白可由于其空间结构的聚会而影响实验室的检测结果,此时应A.将样本先经巯基
2013年1~5月,保险业平均每月业务及管理费用约为多少亿元?A.180
(2020年真题)在基金合同约定之外的日期和时间提出申购、赎回或者转换申请的,作
【背景资料】 某工程项目发包人与承包人签订了施工合同,工期4个月,工程内容包括
最新回复
(
0
)