问题
The Estimate Activity Resource process is closely coordinated with the ( ) process.A.Estimate Costs B.Sequence Activities C.Plan Communications D.Conduct Procurements
选项
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
答案
A
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2295939.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Humanresourcemanagementisthemanagem
( )isaprocessofmonitoringthestatu
( )istheprocessofimplementingrisk
( )istheuseofcomputingresources(h
PerformQualityControlistheprocesso
()istheprocessofidentifyingindivi
Validatescopeistheprocessofformali
Agoalofthe()processistodetermin
The()processanalyzestheeffectofrisk
随机试题
QuantityA:335/999QuantityB:110/333A、QuantityAisgreater.B、QuantityBis
Reebokexecutivesdonotliketoheartheirstylishathleticshoescalled"f
事故调查组应当自()起60d内提交事故调查报告;特殊情况下,经负责事故调查的人民
作为中国传统的经典艺术形式,书法相当独特。事实上,在现当代中国文化遭遇东西文化碰
各种运输方式内外部的各个方面的构成和联系,就是( )。 A.运输系统
计算机语言的发展过程,依次是机器语言、()和高级语言。 A.汇编语言B.编
《巴塞尔新资本协议》中,风险加权资产的计算公式为( )。A.信用风险加权资产+市
下列统计指标中,不能用定距尺度计量的是( )。A.国内生产总值 B.人口数
根据《中华人民共和国银行业监督管理法》,我国的银行业金融机构有()。A.商业银行
依据《建设项目安全设施"三同时"监督管理办法》,下列情形中,已经批准的建设项目及
最新回复
(
0
)