Which of the following scheduling methods uses more of the risk management concepts( ).A.ADM B.PDMC.CPMD.PERT
选项
A.ADM
B.PDM
C.CPM
D.PERT
答案
D
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2301737.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Whichofthefollowingisanimportanti
Alloffollowingsshouldbedonebythe
WhichofthefollowingProjectScopeMan
Whichofthefollowingschedulingmethod
Whichofthefollowingstatementrelated
Whichofthefollowingschedulingmethod
WhichofthefollowingProjectScopeMan
Whichoffollowingisanimportantinput
()isamethodusedinCriticalPathMeth
thefollowingdiagramis()networktopol
随机试题
Whyaretelephonenumberschanging?[br]Youcanminimizethecostifyou[origi
Thispartistotestyourabilitytodopracticalwriting.Youarerequiredtow
Oncetheharddecisionshavebeenmadeabouthowtotreatapatient’scancer
WhichofthefollowingisthenationalflagoftheUnitedStatesofAmerica?[im
金融类不良资产主要操作模式的环节不包括()。A.管理 B.处置 C.收购
市场配置资源本身存在着固有的缺陷,即通常所说的市场失灵。下列关于市场失灵的描述错
为病人做清洁伤口换药时,移开覆盖在伤口的方纱的正确做法是()。A.用手自边缘处
人在每一瞬间,将心理活动选择了某些对象而忽略了另一些对象。这一特点指的是注意的(
在研究消费者行为时,需假定()。A.市场是完全竞争的 B.市场是完全有效的
220kV变电所,一期2×180MVA主变,远景3×180MVA主变。三相有载调
最新回复
(
0
)