Which of the following scheduling method

免费题库2022-08-02  47

问题 Which of the following scheduling methods uses more of the risk management concepts(  ).A.ADM    B.PDMC.CPMD.PERT

选项 A.ADM   
B.PDM
C.CPM
D.PERT

答案 D

解析
转载请注明原文地址:https://tihaiku.com/congyezige/2301737.html