问题
Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()A.Scope PlanningB.Scope VerificationC.Scope Change ControlD.Scope Definition
选项
A.Scope Planning
B.Scope Verification
C.Scope Change Control
D.Scope Definition
答案
D
解析
在以下项目范围管理几个过程中,(74)涉及将主要项目可交付成果细分成更小、更容易管理的组件单元。A.范围规划B.范围确认C.范围变更控制D.范围定义
转载请注明原文地址:https://tihaiku.com/congyezige/2299701.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Inaprojectplan,whentheprojectmana
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Toensuretheprojectteamprovidesthe
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
ChooseTWOletters,A-E.WhichTWOproblemsdoesGroveridentifyconcerningthe
PartyRandomThoughtsLastnight,press
Themanagerrequiredthatalltheemployeesattheofficebefore9:00inthemo
SevenofAmerica’sNaturalWondersNiagaraFallsTheUni
第二次世界大战后,美国、加拿大等许多国家用“文件中心”代替了非终极性机关档案馆。
关于无形资产评估量化资料的说法,错误的是()。A.实体性贬值,功能性贬值和
红细胞目视计数法的计算公式应是(N表示5个中方格内红细胞数)A.N×5×10×1
192、加强对各种车辆维修管理。各种车辆的技术状况应符合国家规定,消防装置完善可
业主大会筹备组的工作职责包括()。A:确定首次业主大会会议召开的时间、地点、形式
下列长期投资决策评价指标中,其数值越小越好的指标是()。A:内部收益率B:投资
最新回复
(
0
)