问题
Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()A.Scope PlanningB.Scope VerificationC.Scope Change ControlD.Scope Definition
选项
A.Scope Planning
B.Scope Verification
C.Scope Change Control
D.Scope Definition
答案
D
解析
在以下项目范围管理几个过程中,(74)涉及将主要项目可交付成果细分成更小、更容易管理的组件单元。A.范围规划B.范围确认C.范围变更控制D.范围定义
转载请注明原文地址:https://tihaiku.com/congyezige/2299701.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Inaprojectplan,whentheprojectmana
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Toensuretheprojectteamprovidesthe
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
WallStreetStocksaremixedwithbluechipsreboundingfrom(1).Rightnow
Hischarmandthefactthatheissolikeableoftenallowshimtoget________wit
Icouldn’ttakemyeyesoffthedriedbloodonhisface,onhisblueshirt,
A.颌内牵引 B.颌间垂直牵引 C.颌外牵引 D.Ⅲ类颌间牵引 E.Ⅱ类
A.最粗粉B.细粉C.粗粉D.极细粉E.最细粉全部通过8号筛的粉末是()。
在我国境内进行的大型基础设施工程建设项目,可以不进行招标的环节是( )。
患者,女性,54岁,一年内反复因情绪波动突发高血压,昏倒,发作时曾自测血压220
(2019年真题)下列关于商业银行国别风险的表述,最不恰当的是()。A.国内信
下列关于消费税的说法,哪一项是错误的?()A.消费税的税基为销售额或销售数量
(2019年真题)O2O电子商务实现线上与线下协调集成,其本质属于()。A
最新回复
(
0
)