Which of the following scheduling method

资格题库2022-08-02  37

问题 Which of the following scheduling methods uses more of the risk management concepts( ) .A.ADMB.PDMC.CPMD.PERT

选项 A.ADM
B.PDM
C.CPM
D.PERT

答案 D

解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299739.html

最新回复(0)