All of followings should be done by the

最全题库2022-08-02  53

问题 All of followings should be done by the project manager during project control except(  )A.determine that a change has occurredB.ensure that a change is agreedC.make sure all changes are approved by managementD.manage changes as they occur

选项 A.determine that a change has occurred
B.ensure that a change is agreed
C.make sure all changes are approved by management
D.manage changes as they occur

答案 C

解析 以下所有应该由项目经理在项目控制中管理,除了(确保所有的改变都经管理层批准)
A.确定已经发生变更
B.确保变更获得同意
C. 确保所有的改变都经管理层批准
D. 管理变更所发生的