All of followings should be done by the project manager during project control except( )A.determine that a change has occurredB.ensure that a change is agreedC.make sure all changes are approved by managementD.manage changes as they occur
选项
A.determine that a change has occurred
B.ensure that a change is agreed
C.make sure all changes are approved by management
D.manage changes as they occur
答案
C
解析
以下所有应该由项目经理在项目控制中管理,除了(确保所有的改变都经管理层批准)
A.确定已经发生变更
B.确保变更获得同意
C. 确保所有的改变都经管理层批准
D. 管理变更所发生的
转载请注明原文地址:https://tihaiku.com/congyezige/2302527.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
随机试题
Ifonlythecommittee______theregulationsandputthemintoeffectassoonas
Withtheeffectsofglobalization,increasesintechnologyandthepaceof
Itisaknownfactthatphysicalactivityimprovesoverallhealth.Notonly
MarsfascinatesscientistsbecauseofitssimilaritytoEarth,anditfasci
哲学物质范畴同自然科学的物质结构理论的关系是()A.整体与部分的关系 B.一般
A. B. C. D.
《医疗事故处理条例》第四条规定:发生导致3人以上人身损害后果的重大医疗过失行为,
任何金融工具都可能出现价格的不利变动而带来资产损失的可能性,这是()。A
场内证券交易实行分级结算,()接受投资者委托达成证券交易,并承担证券或资金的交
知荣明耻,人之根本。荣誉和耻辱,是荣辱观中的一对基本范畴,是指社会对人们行为褒贬
最新回复
(
0
)