All of followings should be done by the project manager during project control except( )A.determine that a change has occurredB.ensure that a change is agreedC.make sure all changes are approved by managementD.manage changes as they occur
选项
A.determine that a change has occurred
B.ensure that a change is agreed
C.make sure all changes are approved by management
D.manage changes as they occur
答案
C
解析
以下所有应该由项目经理在项目控制中管理,除了(确保所有的改变都经管理层批准)
A.确定已经发生变更
B.确保变更获得同意
C. 确保所有的改变都经管理层批准
D. 管理变更所发生的
转载请注明原文地址:https://tihaiku.com/congyezige/2302527.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
随机试题
THEHYDROGENECONOMYItseems-likeeverydaythereisanew
Manytheoriesconcerningthecausesofjuveniledelinquencyfocuseitheron
如图6-6所示,D,E是△.ABC中BC边的三等分点,F是AC的中点,AD与EF
健康管理师张某将客户婚外恋消息透露给他人,侵害了客户下列哪些权利()A.
开放式基金在基金份额认购上的收费模式为( )。A.网上发售模式 B.网下发售
J142、遥信输入回路中常用()作为隔离电路。(A)变压器(B)光电耦合器(
固体废物处理和处置方法中,堆肥方法的不足之处是()。A.占地较大 B.卫
共用题干 某地区进行网民上网方式调查,结果显示,当地网民规模约有400万,其中
用于公路路基的填料要求挖取方便,压实容易,强度高,水稳定性好。其中强度要求是按C
女,30岁,因食欲不振、尿少、腹胀2个月住院。19岁检查时曾发现肝大。体检,消瘦
最新回复
(
0
)