Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.A、Benchmarking B、Quality metric C、Quality checklist D、Brainstorming
选项
A、Benchmarking
B、Quality metric
C、Quality checklist
D、Brainstorming
答案
A
解析
质量规划工具通常是用来帮助计划有效的质量管理活动。()就是一个这样的工具,它是将实际实施过程中或计划之中的项目做法与其他项目进行比较,以便形成改进意见,并为绩效考核提供一个基础。
A、基准分析B、质量度量指标C、质量核对表D、头脑风暴
显然是选A.基准分析(又叫标杆对照)
转载请注明原文地址:https://tihaiku.com/congyezige/2297088.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thehighestlevelofqualitymanagement
Thesevenbasicqualitytoolsareusedw
PlanQualityistheprocessofidentifyi
()isoneofthequalityplanningoutputs
PlanQualityistheprocessofidentifyi
PlanQualityistheprocessofidentifyi
PerformQualityControlistheprocesso
质量功能部署(QualityFunctionDeployment,QFD)将
Qualitymanagementensuresthatanorgan
Qualitymanagementhasfourmaincompon
随机试题
How"SecondBrain"InfluencesMoodandWeil-BeingAsOlympia
Forthispart,youareallowed30minutestowriteacampaignspeechinsupp
Peoplefindthatlikehumanschimpanzees(黑猩猩)use"tools":theystriptwigs
[originaltext]W:Hi.HowcanIhelpyou?M:Yes,(12)I’dliketoreturnthissw
HowtoStandOutatGraduateFairsAmajoreventfor
股票涨跌幅价格的计算公式为()。A:前收盘价*(1±涨跌幅比例) B:前收盘价
甲趁夜深入静时窜人村民乙家中盗取现金一万元,刚要离开,被惊醒的乙发觉,甲为了逃避
影响重金属污染物在包气带土层中迁移的主要因素包括( )。A.水的运移 B.
正常施工条件下,砖墙每日砌筑高度不宜超过()m。A.1.5 B.2.0 C
(2020年真题)关于所有权的说法,正确的有()。A.所有权人对自己的不动产,
最新回复
(
0
)