问题
Quality management has four main components:quality planning .,quality assurance.,quality control and quality().A.improvement B.change C.spiral D.evolution
选项
A.improvement
B.change
C.spiral
D.evolution
答案
A
解析
翻译:它包括四个主要环节:质量计划、
质量保证、质量控制和过程改进。
A. 改进 B.变更 C.升级 D.进化
转载请注明原文地址:https://tihaiku.com/congyezige/2295912.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
()isthecorecomponentofbitcoin。A.
Qualitymanagementensuresthatanorgan
Humanresourcemanagementisthemanagem
Thesevenbasicqualitytoolsareusedw
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalisto
( )istheoutputofthequalityplannin
PlanQualityistheprocessofidentifyi
TheDevelopProjectManagementPlanProc
随机试题
[originaltext]M:I’lltakethesethreebooks.Aretheyfiftycentseach?W:The
[originaltext]W:Goodmorning,listeners.TodayI’dliketointroduceourguest
Ifyouwantotherstorespectyou
根据现行宪法规定,下列说法中,不正确的是:A.中央军事委员会领导全国武装力量
A.维护人民健康权益放在第一位 B.解决损害人民群众切身利益的突出问题 C.
肝硬化食管静脉曲张患者,经非手术疗法后行肠系膜上静脉和下腔静脉吻合术,术后48小
某老师讲授圆的周长时。还介绍了我国古代数学家祖冲之的突出贡献。同学们不仅学会了知
简述现代企业人力资源管理各个历史发展阶段的特点。
cAMP发挥对细胞的调节作用是通过激活 A.蛋白激酶AB.蛋白激酶C C.
某拦河水闸工程,采用一次拦断围堰法施工,围堰为土石围堰。施工过程中发生了如下
最新回复
(
0
)