问题
The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).A.developmentB.conceptC.system analysisD.implementation
选项
A.development
B.concept
C.system analysis
D.implementation
答案
B
解析
参考译文项目的生命周期是对项目各个阶段从开始到结束的描述。下列哪项不是一个阶段的传统项目的生命周期,它是概念阶段。A、开发 B、概念 C、系统分析 D、实施
转载请注明原文地址:https://tihaiku.com/congyezige/2296291.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Inaprojectplan,whentheprojectmana
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Theprojectbudgethasbeenfinalized.Ad
Theprojectscheduleismorethanadocu
( )describes,indetail,theproject’
随机试题
NowmoreandmoreJapanesebusinessesare___________encouragingtheiremployee
Tobefrank,IlikeMrs.Zhang’sclassmostbecauseshecouldspeakEnglishvery
Ourshasbecomeasocietyofemployees.Ahundredyearsorsoagoonlyoneo
Whydoweinvestsomuchhopeinnewtechnologyandwhyarewesodisappoint
[originaltext]Therearedifferentwaystostorefish.Twowaystokeepfish
Theconceptofstudentexchangebetweencountriesisnotanewone.Itisa
()属于IT服务部署实施,验收阶段的活动A.历史运维资料转移 B.编写I
在假设检验中,显著性水平a表示( )。A.P{接受H0|H0为假} B.P{
主控制室屏(台)上应装设的信号有()。 A.断路器位置信号,故障信号、设备发生
计划开工工期是指()。A.合同签字之日 B.合同协议书约定的开工日期 C.
最新回复
(
0
)