In project time management processes,(
In project time management processes,(
练习题库
2022-08-02
41
问题
In project time management processes,( )involves identifying and documenting the relationships between project activities.A.activity definitionB.activity sequencingC.schedule controlD.schedule development
选项
A.activity definition
B.activity sequencing
C.schedule control
D.schedule development
答案
B
解析
活动排列顺序:识别和记录项目活动之间的关系的过程。
转载请注明原文地址:https://tihaiku.com/congyezige/2413112.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
Amanagementinformationsystem()thebus
Amanagementinformationsystem__()__th
Managementinformationsystemsformabe
Amanagementinformationsystem__()__th
Amanagementinformationsystem__(请作答此空)
Managementinformationsystemsformabe
Ravi,likemanyproject( ),hadstudiedt
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique
Aprojectisa[temporary](请作答此空)ofun
随机试题
Accordingtothispassage,thepopulationinsidethecityofShanghaiis______.
准静态过程中,系统的势差或力差( )。A.不可以存在 B.到处可以存在
在定性风险分析中,使用定性分析将风险发生的概率及其后果描述为极高、高、中、低、极
根据是否患有其他慢性病,如糖尿病、高血压、冠心病等,将肥胖分为单纯性肥胖和重症肥
(2014年)下列关于公开发行普通股股票筹资的表述中,错误的是( )。A.与发
我国各族人民之所以能够产生血浓于水的地,海内外华人之所以能够相互合作共同奋斗,从
秦汉时期设立的国家音乐机构是()。A.太常寺 B.乐府 C.鼓吹署
人工智能是指由人工制造出来的系统所表现出来的智能,人工智能的核心问题包括推理、知
不属于申请独立董事的任职资格应当具备的条件的是( )。A.具有从事期货、证券等金
最新回复
(
0
)