首页
登录
从业资格
A project is a [temporary] ( ) of unique
A project is a [temporary] ( ) of unique
题库
2022-08-02
83
问题
A project is a [temporary] ( ) of unique, complex, and connected activities having one goal or purpose and that must be completed by a specific time, within budget, and according to ( ). Project management is the process of scoping, planning, staffing, organizing, directing, and controlling the development of a(n) ( ) system at a minimum cost within a specified time frame. For any systems development project, effective project management is necessary to ensure that the project meets the (请作答此空), is developed within an acceptable budget, and fulfills customer expectations and specifications, Project management is a process that starts at the beginning of a project, extends through a project, and doesn't culminate until the project is completed. The prerequisite for good project management is a well-defined system development process. Process management is an ongoing activity that documents, manages the use of, and improves an organization s chosen methodology (the “process”) for system development, Process management is concerned with the activities, deliverables, and quality standards to be applied to ( ) project(s).A.deadlineB.specificationC.expectationD.requirement
选项
答案
A
解析
表示截止日期的意思。附(参考翻译):一个项目是一个独特的、复杂的、相互关联的活动的[临时]序列,有一个目标或目的,必须在特定的时间、预算内和根据规范完成。项目管理是一个范围界定、计划、人员配置、组织、指导和控制可接受系统开发的过程,在规定的时间内以最低的成本进行。对于任何系统开发项目,有效的项目管理都是必要的,以确保项目在截止日期前完成,在可接受的预算内开发,并满足客户的期望和规范,项目管理是从项目开始时开始的过程,延伸到一个项目中,直到项目完成才达到顶点。良好的项目管理的先决条件是定义良好的系统开发过程。过程管理是一项持续的活动,它记录、管理和改进组织为系统开发所选择的方法(“过程”),过程管理涉及应用于所有项目的活动、可交付成果和质量标准。
转载请注明原文地址:https://tihaiku.com/congyezige/2417367.html
本试题收录于:
中级 软件评测师题库软件水平考试初中高级分类
中级 软件评测师
软件水平考试初中高级
相关试题推荐
Theprojectworkbookisnotsomuchase
Theprojectworkbookisnotsomuchase
Theprojectworkbookisnotsomuchase
能实现UNIQUE约束功能的索引是( );针对复杂的约束,应采用( )来实现
Ravi,likemanyproject( ),hadstudiedt
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
Theprojectworkbookisnotsomuchase
随机试题
A、gotB、stoodC、putB
Peopletendtostrugglewhenlearninganotherlanguage,especiallyiftheya
[originaltext]LasttimeweoutlinedhowtheCivilWarfinallygotstarted.
[originaltext]Researchindicatesthatparentswhorewardself-controlandi
结合有关数理统计方法评定项目及规定内容,回答下列有关问题。(2)当混凝土强度等级
患者女,44岁,因左上后牙疼痛剧烈,有伸长感1天就诊。查体:远中邻面深龋,穿髓,
股疝一旦嵌顿,可迅速发展为A、易复性疝 B、难复性疝 C、滑动性疝 D、嵌
指数的实质是相对数,它能反映现象的变动和差异程度。()
根据《市政公用设施抗灾设防管理规定》,下列选项中不正确的是( )。A.市政公用
二战后,联邦德国政府采用路德维希·艾哈德博士的经济改革方针,推行“社会市场经济”
最新回复
(
0
)