问题 In a project plan, when the project manager schedules activities, he (or she) often uses ( ) method, precedence relationships between activities are represented by circles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity.A.causality diagramB.Gantt chartC.histogramD.arrow diagram

选项 A.causality diagram
B.Gantt chart
C.histogram
D.arrow diagram

答案 D

解析 翻译:在项目计划中,当项目经理安排活动时,他(或她)经常使用 ( ) 的方法,将活动之间的优先级关系用一个或多个箭头连接的图来表示。箭头的长度代表相关活动的持续时间。A.因果图        B.甘特图  C.柱状图        D.箭线图