首页
登录
从业资格
You are a project manager for a small pr
You are a project manager for a small pr
题库
2022-08-02
102
问题
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as ( ) .A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided
选项
A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided
答案
B
解析
你是一个小项目的项目经理,项目的预算是50万元,工期是6个星期。到今天为止,你花费了26万元,而预算应完的工作对应的值为28万元,根据你的计划进度,你应在此时花费30万,基于这些情况,你的项目极可能落后于进度。
正确选项B。
转载请注明原文地址:https://tihaiku.com/congyezige/2413506.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
以下不属于信息系统项目管理工具的是()。A.MicrosofiProject
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
在下图一的SNMP配置中,能够响应Manager2的getRequest请求的是
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique,co
随机试题
AttheuniversitywhereIteach,fewerandfewernewbooksareavailablefro
[originaltext]TherearesomeseriousproblemsintheBiramichiRiver.Thel
基准线测量时,通常采用返侧丈量,为保证量距精度,最少应测量()测回。A、一
共用题干 SavingaCity'sPublicArtAvoiding
( )对本单位会计工作和会计资料的真实性和完整性负主要责任。A.相关的会计人员
论述法律原则的作用。
下列关于差量分析法的说法中,不正确的是( )。A.差量分析法是对备选方案差额利润
监理规划中的投资、进度、质量目标控制方法和措施应包括()等内容。 A.
为防止隧道衬砌施工中裂缝的产生,衬砌厚度应根据( )确定。A.衬砌混凝土的强度
项目管理信息系统通常包括有()子系统。A.进度管理 B.质量管理 C.查询功
最新回复
(
0
)