首页
登录
从业资格
You are a project manager for a small pr
You are a project manager for a small pr
题库
2022-08-02
88
问题
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as ( ) .A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided
选项
A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided
答案
B
解析
你是一个小项目的项目经理,项目的预算是50万元,工期是6个星期。到今天为止,你花费了26万元,而预算应完的工作对应的值为28万元,根据你的计划进度,你应在此时花费30万,基于这些情况,你的项目极可能落后于进度。
正确选项B。
转载请注明原文地址:https://tihaiku.com/congyezige/2413506.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
以下不属于信息系统项目管理工具的是()。A.MicrosofiProject
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
在下图一的SNMP配置中,能够响应Manager2的getRequest请求的是
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique,co
随机试题
Learningtoplayamusicalinstrumentcanchangeyourbrain,withaUSrevie
WhytheSuper-RichAren’tLeavingMuchofTheirFortunestoTheirKidsA
[originaltext]M:Howdoyoufindyourballetlessons?W:Theyarewellworththe
“有用”对思维而言是一种巨大的________,很容易让我们摒弃理性,走向___
已知某符号的编码为“0100101”,若增加一个偶校验位,则其编码变为()。A.
网络安全应用协议SSL协议工作在( ),HTTPS协议工作在( )。 问题
商业银行进行贷款审批时,要遵循的原则有()。A.诚信审贷 B.审贷分离 C
下列关于期货公司提供交易咨询服务的表述,错误的是( ).A.期货公司应当与客户
资产是指企业现时的交易或者事项形成的、由企业拥有或者控制的、预期会给企业带来经济
下列关于平行承发包模式的说法中,正确的有()A.对业主投资的早期控制不利
最新回复
(
0
)