You are a project manager for a small pr

题库2022-08-02  63

问题 You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (  ) .A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided

选项 A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided

答案 B

解析 你是一个小项目的项目经理,项目的预算是50万元,工期是6个星期。到今天为止,你花费了26万元,而预算应完的工作对应的值为28万元,根据你的计划进度,你应在此时花费30万,基于这些情况,你的项目极可能落后于进度。
正确选项B。
转载请注明原文地址:https://tihaiku.com/congyezige/2413506.html

最新回复(0)