首页
登录
从业资格
You are a project manager for a small pr
You are a project manager for a small pr
题库
2022-08-02
72
问题
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as ( ) .A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided
选项
A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided
答案
B
解析
你是一个小项目的项目经理,项目的预算是50万元,工期是6个星期。到今天为止,你花费了26万元,而预算应完的工作对应的值为28万元,根据你的计划进度,你应在此时花费30万,基于这些情况,你的项目极可能落后于进度。
正确选项B。
转载请注明原文地址:https://tihaiku.com/congyezige/2413506.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
以下不属于信息系统项目管理工具的是()。A.MicrosofiProject
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
在下图一的SNMP配置中,能够响应Manager2的getRequest请求的是
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique,co
随机试题
A.provideB.neverC.whetherD.explanationE.embarrassingF.neither
BidNoCNCWB051011NoticeofInvitationforBidsFourthRuralWaterSupplyandS
Childrenare【C1】______seriousillnessesbecauseoftheirparentssmokingat
OrganizingofYourSpeechIfyouthumbthroughanymailo
Thinkbeforeyoupost.Youmightnotbeawareofhowmuchinformationyou’re
A.110 B.-110 C.220 D.-220 E.0
下列关于室外消防给水管道的布置和室内、外消火栓设置的说法哪几项正确?( )A.
旅行社经营风险的可能性评价方法有( )。A.风险概率评价法 B.净现值评价法
改革开放40年,我国在发展经济同时,大力推进国家治理体系和治理能力现代化,着力抓
能够切割不锈钢、铝、铜、铸铁、陶瓷和水泥等材料的切割方法为( )。A.氧熔剂切割
最新回复
(
0
)