首页
登录
从业资格
You are a project manager for a small pr
You are a project manager for a small pr
题库
2022-08-02
92
问题
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as ( ) .A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided
选项
A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided
答案
B
解析
你是一个小项目的项目经理,项目的预算是50万元,工期是6个星期。到今天为止,你花费了26万元,而预算应完的工作对应的值为28万元,根据你的计划进度,你应在此时花费30万,基于这些情况,你的项目极可能落后于进度。
正确选项B。
转载请注明原文地址:https://tihaiku.com/congyezige/2413506.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
以下不属于信息系统项目管理工具的是()。A.MicrosofiProject
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
在下图一的SNMP配置中,能够响应Manager2的getRequest请求的是
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique,co
随机试题
A、gotB、stoodC、putB
Peopletendtostrugglewhenlearninganotherlanguage,especiallyiftheya
[originaltext]LasttimeweoutlinedhowtheCivilWarfinallygotstarted.
[originaltext]Researchindicatesthatparentswhorewardself-controlandi
结合有关数理统计方法评定项目及规定内容,回答下列有关问题。(2)当混凝土强度等级
患者女,44岁,因左上后牙疼痛剧烈,有伸长感1天就诊。查体:远中邻面深龋,穿髓,
股疝一旦嵌顿,可迅速发展为A、易复性疝 B、难复性疝 C、滑动性疝 D、嵌
指数的实质是相对数,它能反映现象的变动和差异程度。()
根据《市政公用设施抗灾设防管理规定》,下列选项中不正确的是( )。A.市政公用
二战后,联邦德国政府采用路德维希·艾哈德博士的经济改革方针,推行“社会市场经济”
最新回复
(
0
)