首页
登录
从业资格
You are a project manager for a small pr
You are a project manager for a small pr
题库
2022-08-02
95
问题
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as ( ) .A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided
选项
A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided
答案
B
解析
你是一个小项目的项目经理,项目的预算是50万元,工期是6个星期。到今天为止,你花费了26万元,而预算应完的工作对应的值为28万元,根据你的计划进度,你应在此时花费30万,基于这些情况,你的项目极可能落后于进度。
正确选项B。
转载请注明原文地址:https://tihaiku.com/congyezige/2413506.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
以下不属于信息系统项目管理工具的是()。A.MicrosofiProject
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
在下图一的SNMP配置中,能够响应Manager2的getRequest请求的是
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique,co
随机试题
HowdidAmandagetthemovietickets?[br][originaltext]M:Amanda,didyouche
Questions29-40•Readtheinformationaboutcommercialbanks.•Choose
治疗肺炎球菌肺炎时首选下列哪种药物A.丁胺卡那 B.青霉素G C.庆大霉素
??陕西某高校一位副教授因高热住进职工医院,经B超、CT、抽血、抽骨髓化验等检
在工程实践中,焊接工艺评定的标准应根据产品、施工项目性质和行业的不同,按照设计文
下列关于工业建筑及总平面设计中的场地要求的表述中,正确的是()。A.不适应物
期货公司应当定期向中国期货保证全监控中心提交客户的影像资料,包话()A.个人
以下哪个囊肿X线检查无改变A.鼻腭囊肿 B.正中囊肿 C.球上颌囊肿 D.
下列说法中属于观察法缺点的是( )。A.只能描述现象而难以说明原因 B.调研
建立国土空间规划体系并监督实施,将( )等空间规划融合为统一的国土空间规划,实
最新回复
(
0
)