critical path for a project is the series of activities that determine( )by which the projectcan be completed.A.the earliest timeB.the latest timeC.the total timeD.the free time
选项
答案
A
解析
关键路径通常由一系列决定项目工期的活动组成,它们决定了整个项目的最早完成时间。
转载请注明原文地址:https://tihaiku.com/congyezige/2411908.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
heprojectworkbookisnotsomuchasep
Aprojectisa[temporary]()ofunique
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary](请作答此空)ofuniqu
Inprojecttimemanagementprocesses,(
Acriticalpathforaprojectistheser
随机试题
【S1】[br]【S2】called
Governmenthastraditionallybeenevaluatedintermsoftheireffectsinprom
Whenwethinkofoil,thepartoftheworldthatcomestomindfirstmaybe
LatertheGreeksmovedeastfromCumaetoNeapolis,theNewCity,alittlefa
[originaltext]M:I’mexhausted!Ican’tseestraightanymore.W:Callitaday
小学音乐《大家来唱》 一、考题回顾
公司债券按是否记名,分为记名债券和信用债券。
公司成立后,公司、股东或者公司债权人可以请求认定相关股东抽逃出资的有()。
关于胆管癌,下列哪项叙述不正确A.上段胆管癌最为常见 B.多为腺癌 C.主要
男,25岁。腰背部疼痛8年,晨起明显,活动后减轻,近1个月腰痛加重,活动受限。查
最新回复
(
0
)