首页
登录
从业资格
critical path for a project is the serie
critical path for a project is the serie
考试题库
2022-08-02
23
问题
critical path for a project is the series of activities that determine( )by which the projectcan be completed.A.the earliest timeB.the latest timeC.the total timeD.the free time
选项
答案
A
解析
关键路径通常由一系列决定项目工期的活动组成,它们决定了整个项目的最早完成时间。
转载请注明原文地址:https://tihaiku.com/congyezige/2411908.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
heprojectworkbookisnotsomuchasep
Aprojectisa[temporary]()ofunique
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary](请作答此空)ofuniqu
Inprojecttimemanagementprocesses,(
Acriticalpathforaprojectistheser
随机试题
HowtoSolveResearchProblems?I.【T1】______【T1】______—Problem:hardtodevis
Althoughreceivingfinancialsupportfromfamily,community,orthegovernmentis
TypesofClimateClimateisthecombinationoftem
Toitsfans,itisaddictive.Tothemedia,itisapromisingmoney-maker.S
Thereaxe【B1】______researchmethodsyoucanuseto【B2】______information.As
下列高层建筑防火分区防火墙设计中错误的是( )。
资产评估中可以作为资产边界的依据为()。A、所有权 B、资产的产权 C、经
下列法律中,属于宪法相关法的是( )。 A、《行政复议法》 B、《行政处
全国上下继续心往一处想,劲往一处使,拧成一股绳,把抗震救灾作为头等大事,汇集力量
在计算项目的投资利税率时,不包含增值税。()
最新回复
(
0
)