A critical path for a project is the ser

练习题库2022-08-02  10

问题 A critical path for a project is the series of activities that determine(  ) by which the project can be completed.A.the earliest timeB.the latest timeC.the total timeD.the free time

选项 A.the earliest time
B.the latest time
C.the total time
D.the free time

答案 A

解析 关键路径法是估算项目最短工期,确定逻辑网络路径的进度灵活性大小的一种方法。