( )is a method used in Critical Path Me
( )is a method used in Critical Path Me
资格题库
2022-08-02
49
问题
( )is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.A.PERTB.AOAC.WBSD.PDM
选项
A.PERT
B.AOA
C.WBS
D.PDM
答案
D
解析
PDM用于关键路径法,是用于编制项目进度网络图的一种方法,它使用方框或者长方形(被称作节点)代表活动,它们之间用箭头连接,显示彼此之间存在的逻辑关系。
转载请注明原文地址:https://tihaiku.com/congyezige/2302018.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
()isamethodusedinCriticalPathMeth
Whichofthefollowingschedulingmethod
()isamethodusedinCriticalPathMeth
()amethodofobtainingearlyfeedbacko
PrecedenceDiagrammingMethod(PDM)isa
Projectselectionmethodsinvolvemeasur
PrecedenceDiagrammingMethod(PDM)isa
()amethodofobtainingearlyfeedback
Projectselectionmethodsinvolvemeasur
PDMisamethodofconstructingaprojec
随机试题
Allyoudonowis______yourhomework.A、completeB、completingC、havingcomplete
[originaltext]W:Hello,Iboughtthislaptopcomputeralittleoveramonthago
强化enhance;strengthen
Therearetwofactorswhichdetermineanindividual’sintelligence.Thefirs
[originaltext]W:Haveyoufoundanythingwrongwithmyteeth?M:Notyet.I’ms
根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013,下列脚手架中以
48岁,男性,肝硬化患者,有腹水。不规则服用利尿剂治疗,二天来出现嗜睡。体检:轻
从所给的四个选项中,选择最合适的一个填入问号处,使之呈现一定的规律性: A.如
社会救助是指国家通过国民收入的再分配对因自然灾害或其他经济、社会原因而无法维持最
根据《建设工程监理规范》(GB/T50319-2013),工程建设监理规划应当
最新回复
(
0
)