Precedence Diagramming Method(PDM) is a
Precedence Diagramming Method(PDM) is a
admin
2022-08-02
50
问题
Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish
选项
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
答案
A
解析
前导图(PDM)是一种活动排序的方法。在PDM中可以使用四种不同的逻辑关系。如果后继活动的开始依赖于紧前活动的结束,则称之为完成对开始的关系。
A.完成对开始B.完成对完成C.开始对开始D.开始对完成
转载请注明原文地址:https://tihaiku.com/congyezige/2297012.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )isamethodusedinCriticalPathMe
Whichofthefollowingschedulingmethod
Whichofthefollowingschedulingmethod
()isamethodusedinCriticalPathMeth
()amethodofobtainingearlyfeedbacko
PrecedenceDiagrammingMethod(PDM)isa
Projectselectionmethodsinvolvemeasur
()amethodofobtainingearlyfeedback
Projectselectionmethodsinvolvemeasur
PDMisamethodofconstructingaprojec
随机试题
Idon’toftenlosethingsandI’mespeciallycarefulwithmoney,so1wasqui
Theworld-famousBelgianhasarrivedinBritainwithhisequallyfamousdog
室内消火栓系统设置消防水泵接合器的条件,以下哪条错误?( )A.超过2层或建筑
按照行政法规、中国证监会有关要求,中国证券业协会行使的职责有()。 ①制定证
钢筋混凝土梁中配置箍筋主要目的是( )。 A、提高正截面承载力 B、提高
除法律另有规定外,违法行为在一定期限内未被行政机关发现的,不再给予行政处罚。该期
某场地地层构成如下:第一层为粉土,厚度5m;第二层为黏土,厚度4m;两层土的天然
(2020年真题)2020年1月8日,甲公司成立,张某为法定代表人,李
制约项目组织计划制订的主要因素包括()。A.项目的组织结构 B.共同达成的有关
属继发性肾小球疾病的是 A.系统性红斑狼疮性肾炎 B.多囊肾 C.
最新回复
(
0
)