首页
登录
从业资格
Precedence Diagramming Method(PDM) is a
Precedence Diagramming Method(PDM) is a
admin
2022-08-02
99
问题
Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish
选项
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
答案
A
解析
前导图(PDM)是一种活动排序的方法。在PDM中可以使用四种不同的逻辑关系。如果后继活动的开始依赖于紧前活动的结束,则称之为完成对开始的关系。
A.完成对开始B.完成对完成C.开始对开始D.开始对完成
转载请注明原文地址:https://tihaiku.com/congyezige/2297012.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )isamethodusedinCriticalPathMe
Whichofthefollowingschedulingmethod
Whichofthefollowingschedulingmethod
()isamethodusedinCriticalPathMeth
()amethodofobtainingearlyfeedbacko
PrecedenceDiagrammingMethod(PDM)isa
Projectselectionmethodsinvolvemeasur
()amethodofobtainingearlyfeedback
Projectselectionmethodsinvolvemeasur
PDMisamethodofconstructingaprojec
随机试题
Manyteenagersthinkthat______canunderstandthembetter.[br]______isve
WhyisitdifficultforvisitorstolocateCambridgeUniversity?[br][original
Industryshouldgetridofhalfitsbosses,saysbehavioralpsychologistA
编码为C8的施工资料是()资料。A.施工记录 B.施工试验记录及检测报告 C
北京人已学会人工取火,晚期智人阶段形成了语言。( )
脊髓空洞症的感觉障碍常常是A、神经干型 B、末梢型 C、分离型 D、后根型
与月经产生没有直接关系的脏腑是A.肾 B.肺 C.胆 D.脾 E.胃
企业会计确认、计量和报告应当以会计主体、持续经营、会计分期和货币计量为会计基本假
在任何历史时期,教育都应先于经济而发展
某施工企业年初从银行借款200万元,按季度计息并支付利息,季度利率为1.5%,则
最新回复
(
0
)