首页
登录
从业资格
Precedence Diagramming Method(PDM) is a
Precedence Diagramming Method(PDM) is a
admin
2022-08-02
58
问题
Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish
选项
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
答案
A
解析
前导图(PDM)是一种活动排序的方法。在PDM中可以使用四种不同的逻辑关系。如果后继活动的开始依赖于紧前活动的结束,则称之为完成对开始的关系。
A.完成对开始B.完成对完成C.开始对开始D.开始对完成
转载请注明原文地址:https://tihaiku.com/congyezige/2297012.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )isamethodusedinCriticalPathMe
Whichofthefollowingschedulingmethod
Whichofthefollowingschedulingmethod
()isamethodusedinCriticalPathMeth
()amethodofobtainingearlyfeedbacko
PrecedenceDiagrammingMethod(PDM)isa
Projectselectionmethodsinvolvemeasur
()amethodofobtainingearlyfeedback
Projectselectionmethodsinvolvemeasur
PDMisamethodofconstructingaprojec
随机试题
InterpretthefollowingpassagesfromChineseintoEnglish.Startinterpretin
[originaltext]Interviewer(W)RichardJohnson(M)Now,listentoPartOne
Comeandseemewhenever_________.A、youareconvenientB、youwillbeconvenient
Inbringingupchildren,everyparentwatcheseagerlythechild’sacquisitio
下面关于神经性厌食的治疗措施,哪项是正确的?A.可使用抗精神药物或抗抑郁药物
问卷是健康风险评估进行信息收集的一个重要手段,通常所需的信息包括()A.生理
下列不属于社区学习资源的是()A.报刊与杂志 B.田间与山丘 C.动物园
下列关于普通消防站责任区划分的表述,正确的是()。(2019年真题)A.按
锚喷暗挖法工作井是为隧道施工而设置的竖向通道,一般采用( )施工。A.支架法
根据《公路水运工程安全生产监督管理办法》、《生产安全事故应急预案管理办法》,公路
最新回复
(
0
)