Precedence Diagramming Method(PDM) is a
Precedence Diagramming Method(PDM) is a
admin
2022-08-02
81
问题
Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish
选项
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
答案
A
解析
前导图(PDM)是一种活动排序的方法。在PDM中可以使用四种不同的逻辑关系。如果后继活动的开始依赖于紧前活动的结束,则称之为完成对开始的关系。
A.完成对开始B.完成对完成C.开始对开始D.开始对完成
转载请注明原文地址:https://tihaiku.com/congyezige/2297012.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )isamethodusedinCriticalPathMe
Whichofthefollowingschedulingmethod
Whichofthefollowingschedulingmethod
()isamethodusedinCriticalPathMeth
()amethodofobtainingearlyfeedbacko
PrecedenceDiagrammingMethod(PDM)isa
Projectselectionmethodsinvolvemeasur
()amethodofobtainingearlyfeedback
Projectselectionmethodsinvolvemeasur
PDMisamethodofconstructingaprojec
随机试题
Modemcowboyseemtobegivingupthebandanna(印花大手帕)handkerchief;yetthe
IntheUnitedStatesthefirstdaynurserywasopenedin1854.Nurserieswer
下列各项不属于常用的脱产培训方法的是( )。A.授课法 B.情景模拟法 C
制定专业人才培养目标的依据不包含()A.国家的教育方针 B.高等教育的总体培
(2013年真题)脚手架大横杆的对接、搭接应符合的规定是()。A.纵向水平杆的
肝郁泄泻的主方是A.葛根芩连汤 B.藿香正气散 C.痛泻要方 D.
如今各地都面临着同样的问题。有的地方看不到自己的优势,____,无法培育新的经济
中国甲公司与德国乙公司进行一项商事交易,约定适用英国法律。后双方发生争议,甲公司
(2017真题)某公司正在论证某生产线改造项目的可行性,经测算,项目完成后生产线
对疑似甲类传染病患者予以隔离所体现的公共卫生伦理原则是( )。A.社会公益
最新回复
(
0
)