首页
登录
从业资格
Precedence Diagramming Method(PDM) is a
Precedence Diagramming Method(PDM) is a
admin
2022-08-02
55
问题
Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish
选项
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
答案
A
解析
前导图(PDM)是一种活动排序的方法。在PDM中可以使用四种不同的逻辑关系。如果后继活动的开始依赖于紧前活动的结束,则称之为完成对开始的关系。
A.完成对开始B.完成对完成C.开始对开始D.开始对完成
转载请注明原文地址:https://tihaiku.com/congyezige/2297012.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )isamethodusedinCriticalPathMe
Whichofthefollowingschedulingmethod
Whichofthefollowingschedulingmethod
()isamethodusedinCriticalPathMeth
()amethodofobtainingearlyfeedbacko
PrecedenceDiagrammingMethod(PDM)isa
Projectselectionmethodsinvolvemeasur
()amethodofobtainingearlyfeedback
Projectselectionmethodsinvolvemeasur
PDMisamethodofconstructingaprojec
随机试题
Invain______togetintouchwiththeEmbassy.A、theytriedB、triedtheyC、did
HowCouldYourHobbyBetheKeytoFinancialSuccess?[A]Virtuallye
FourMinutesthatGetYouHiredBayStateralw
Directions:Forthispart,youareallowed30minutestowriteanadvertisem
关于砖砌体房屋结构中混凝土圈梁的说法,错误的是( )。A.屋盖及每层楼盖处的外
下列情形中,应实地采用解析法重新进行地籍测量,并利用变更地籍测量成果取代原成果的
汾酒的香型属于( )A.酱香型 B.米香型 C.窖香型 D.清香型
(1)白色轿车紧急刹车(2)红色轿车从东往西通过十字路口(3)红色轿车的保险杠
无论何种记账凭证都必须签名或盖章的人员不包括()。A.出纳人员 B.
某钢筋混凝土方形柱为偏心受拉构件,安全等级为二级,柱混凝土强度等级C30,截面尺
最新回复
(
0
)