问题
Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish
选项
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
答案
A
解析
前导图(PDM)是一种活动排序的方法。在PDM中可以使用四种不同的逻辑关系。如果后继活动的开始依赖于紧前活动的结束,则称之为完成对开始的关系。
A.完成对开始B.完成对完成C.开始对开始D.开始对完成
转载请注明原文地址:https://tihaiku.com/congyezige/2297012.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )isamethodusedinCriticalPathMe
Whichofthefollowingschedulingmethod
Whichofthefollowingschedulingmethod
()isamethodusedinCriticalPathMeth
()amethodofobtainingearlyfeedbacko
PrecedenceDiagrammingMethod(PDM)isa
Projectselectionmethodsinvolvemeasur
()amethodofobtainingearlyfeedback
Projectselectionmethodsinvolvemeasur
PDMisamethodofconstructingaprojec
随机试题
Whatwasthespeaker’sfriend?[originaltext]Afriendofminewasgivingan
【S1】[br]【S6】H
Shewastheonlyoneofmefewgirlswho______passedtheexamination.A、wasB、wer
AssistanttoPublicRelationsManagerBusines
HowtoSolveThreePuzzlesNewknowledgeandsophisticat
某机电安装公司施工任务虽已经饱满,但投标工程利润丰厚,为不让企业超负荷运转,决定
与慢性粒细胞白血病血象不符合的是A.嗜碱粒细胞可高达10%~20%B.白细胞数量
根据现代企业制度,公司的权力机构是()。A.股东大会 B.董事会 C.
患者,女性,12岁,3周前患急性扁桃体炎。突然出现窦性心动过速,心搏微弱,心尖区
患者,女性,57岁,2周前出现间断无痛性全程血尿,近2天来加重伴有血块,B型超声
最新回复
(
0
)