Precedence Diagramming Method(PDM) is a

考试题库2022-08-02  34

问题 Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).A.Finish-to-Start  B.Finish-to-Finish  C.Start-to-Start  D.Start-to-Finish

选项 A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish

答案 A

解析 前导图法是用于活动排序的技术。前导图法包括四种活动依赖关系。先行活动结束后续活动才能开展的关系是结束—开始关系。
转载请注明原文地址:https://tihaiku.com/congyezige/2295978.html

最新回复(0)