The inputs of developing project management plan do not include ( ).A.project charterB.stakeholder management strategyC.project scope statementD.outputs from planning processes
选项
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
答案
B
解析
制定项目管理计划的输入不包括:
A. 项目章程
B. 干系人管理
C. 项目范围说明书
D. 其他子计划过程输出
不包括项目干系人管理,答案为B
转载请注明原文地址:https://tihaiku.com/congyezige/2301964.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Configurationmanagementisfocusedont
Inprojectmanagementandsystemsengine
Humanresourcemanagementisthemanagem
( )isaprocessofdevelopingadetail
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
( )managementincludesnegotiatingthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
Establishingaproject( )involveslis
随机试题
Afterhavingassuredtheirreturnjourney,thewriterandhiscompanioncould
Yesterday’sstrikecausedthemostconfusionfor[br][originaltext]Moret
Theideabehindthe"ruleoflaw"isthatimpartiallaws,nothumanbeingsw
Ifyou_________yourdemand,thenmaybeyouwillhavemorechanceofgettingwh
WhenyoumakeyourtravelarrangementstoOxford,Ohio,youshouldmakeplans
下列哪项不是阴虚发热的临床表现A.午后潮热 B.夜间发热 C.时觉身热 D
我国开始发行凭证式国债是在()。A:1950年 B:1981年 C:199
患者,男性,52岁。确诊为肝性脑病,现给予乳果糖口服,目的是为了( )。A.导
因产品存在缺陷造成损害要求赔偿的诉讼时效期间为()年,自当事人知道或者应当知道其
某公司位于A省,为增值税一般纳税人,在B省有一分公司,该分公司为小规模纳
最新回复
(
0
)