The inputs of developing project managem

最全题库2022-08-02  55

问题 The inputs of developing project management plan do not include (  ).A.project charterB.stakeholder management strategyC.project scope statementD.outputs from planning processes

选项 A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes

答案 B

解析 制定项目管理计划的输入不包括:
A. 项目章程
B. 干系人管理
C. 项目范围说明书
D. 其他子计划过程输出
不包括项目干系人管理,答案为B
转载请注明原文地址:https://tihaiku.com/congyezige/2301964.html