The inputs of developing project management plan do not include ( ).A.project charterB.stakeholder management strategyC.project scope statementD.outputs from planning processes
选项
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
答案
B
解析
制定项目管理计划的输入不包括:
A. 项目章程
B. 干系人管理
C. 项目范围说明书
D. 其他子计划过程输出
不包括项目干系人管理,答案为B
转载请注明原文地址:https://tihaiku.com/congyezige/2301964.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Configurationmanagementisfocusedont
Inprojectmanagementandsystemsengine
Humanresourcemanagementisthemanagem
( )isaprocessofdevelopingadetail
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
( )managementincludesnegotiatingthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
Establishingaproject( )involveslis
随机试题
RowanTorrezwillneverbeabletobearhislate(已故的)fathertellhimthathe
PASSAGETHREE[br]Accordingtothepassage,whatistherealimportanceofthe
Neurotechnologyhaslongbeenafavoriteofscience-fictionwriters.InNeuro
一般情况下,非溶性液体着火可使用()来进行火灾的扑救。A.普通泡沫 B.
()支座沉陷不引起内力变化。A.超静定结构 B.静定结构 C.两铰拱
由北京运往旧金山一箱贵重货物,毛重32.0kg,体积尺寸为61cm×51cm×4
2000-143.属于汗法的方剂是 A.杏苏散B.川芎茶调散C.香薷散D
A. B. C. D.
【背景资料】 A安装公司承包某大楼的空调设备的智能监控系统安装工程。主要监控
【简要病史】 男性,26岁,急性腹痛、呕吐、无排便排气3天。
最新回复
(
0
)