问题
The inputs of developing project management plan do not include ( ).A.project charterB.stakeholder management strategyC.project scope statementD.outputs from planning processes
选项
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
答案
B
解析
制定项目管理计划的输入不包括:
A. 项目章程
B. 干系人管理
C. 项目范围说明书
D. 其他子计划过程输出
不包括项目干系人管理,答案为B
转载请注明原文地址:https://tihaiku.com/congyezige/2301964.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Configurationmanagementisfocusedont
Inprojectmanagementandsystemsengine
Humanresourcemanagementisthemanagem
( )isaprocessofdevelopingadetail
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
( )managementincludesnegotiatingthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
Establishingaproject( )involveslis
随机试题
A.heightB.compensateC.whereasD.imbibeE.reflectF.degreeG.strategyH.
Itisclearthatsomepeoplewhoparticipateinexercisetrainingwilldevel
Peopledomanydifferentthingstostayhealthy.Whatdoyoudoforgoodhea
ThissummerIwenttoItalyforwhatturnedtobeathree-weektripwithafr
下列哪几项说法不符合有关蒸汽采暖系统设计的规定?A.蒸汽采暖系统不应采用铸铁柱形
患者,男,68岁。有慢支病史10年。近半年间歇性下肢浮肿,朝轻暮重。X线提示慢支
共用题干 UnderstandingAutism1.Autism(孤独症)
干式变压器、电流互感器等电气设备宜配置()灭火器。(A)移动式干粉(B
某期货公司客户收到期货公司追加保证金通知,该客户保证尽快补齐,第二日该客户并未追
数值变量资料频数表中,组中值的计算公式中错误的是A.本组段上限值-组距/2 B
最新回复
(
0
)