In project network diagram , the number of critical path is ( )。A.noneB.only oneC.only twoD.one or more
选项
答案
D
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2301865.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inprojectmanagementandsystemsengine
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Theprojectbudgethasbeenfinalized.Ad
随机试题
[originaltext]ThenumberofspeakersofEnglishinShakespeare’stimeise
LanguagesinAmericaTheUnitedStatesis【T1】______anEnglishspeakingc
ThejoyousMid-AutumnFestivaliscelebratedonthefifteenthdayofthe
Everyonelivinginthissocietyshouldcommunicatewitheachother.Theyge
单相流体外掠管束换热过程中,管束的排列、管径、排数以及雷诺数的大小均对表面传热系
下列关于川芎的有效成分,错误的是A.川芎嗪B.挥发油C.生物碱D.阿魏酸E.山柰
依据国家电网公司变电检测通用管理规定,停电试验工作,()必须到现场进行验收;
下列关于劳动定额法的说法,错误的是( )。A.劳动定额法是比较传统的绩效考评方
简述职业生涯管理中员工个人方面的管理重点。
关于排卵,正确的是A.排卵多发生在下次月经来潮前14天左右 B.妇女自青春期开
最新回复
(
0
)