A project manager believes that modifyin
A project manager believes that modifyin
练习题库
2022-08-02
69
问题
A project manager believes that modifying the scope of the project may provideadded value service for the customer.The project manager should()A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
选项
答案
D
解析
项目经理认为调整项目范围可以给客户提供增值的服务,项目经理应该怎么做。选项 A 是安排任务变更到项目成员,选项 B 是召集变更控制委员会会议,选项 C是变更项目基线,选项 D 是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择 D。
转载请注明原文地址:https://tihaiku.com/congyezige/2301791.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
WhichofthefollowingProjectScopeMan
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
随机试题
Readthearticlebelowaboutlanguagelearningforsmallbusinesses.For
TheWorldBank’sRealProblemTheWorldBankisundeniablyincrisis.Bu
某危险化学品生产企业,有北区、中区和南区3个生产厂区,北区有危险化学品库房,包括
下列各项中,审计人员可以据以判断生产与存货循环内部控制风险较高的有()A、内部审
A.外阴炎 B.滴虫性阴道炎 C.外阴阴道假丝酵母菌病 D.前庭大腺囊肿
在用GB/T2828.1进行检验时,对一次正常检验状态下的连续批: 当采用
绩效考评面谈在绩效管理( )进行。A.初期 B.进行中 C.末期
党的十七大报告指出,加快推进以改善民生为重点的社会建设,除努力使全体人民学有所教
签发支票时。2100.07元的大写金额正确的是( )。A.贰仟壹佰元零柒分正
下列关于施工组织设计的说法中,错误的是()。A.工程采购合同和设计文件属于
最新回复
(
0
)