问题 A project manager believes that modifying the scope of the project may provideadded value service for the customer.The project manager should()A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

选项

答案 D

解析 项目经理认为调整项目范围可以给客户提供增值的服务,项目经理应该怎么做。选项 A 是安排任务变更到项目成员,选项 B 是召集变更控制委员会会议,选项 C是变更项目基线,选项 D 是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择 D。