首页
登录
从业资格
The earned value technique is a commonly
The earned value technique is a commonly
练习题库
2022-08-02
48
问题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ) .A.he project is ahead of its planned scheduleB.less work was completed than was planned tC.the cost overrun for work completedD.the cost underrun of performance to date
选项
A.he project is ahead of its planned schedule
B.less work was completed than was planned t
C.the cost overrun for work completed
D.the cost underrun of performance to date
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299763.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
Ascheduleiscommonlyusedinprojectp
Theearnedvaluetechniqueisacommonly
Ethernetisthecommonlyusedlocalarea
Ethernetisthecommonlyusedlocalarea
()isaprojectmanagementtechniquefor
Aprojectmanagementtechniquethatisc
Theearnedvaluetechniqueisacommonly
Earnedvaluemanagement(EvM)integrates
Ethernetisthecommonlyusedlocalarea
随机试题
MEDICINE:DOSE::A、surgeon:scalpelB、paper:reamC、treatment:hospitalD、oc
[originaltext]M:Howisschoolgoing,Barbara?Areyoutakinganynewclasses?
参数a取何值时,线性方程组有无数个解?并求其通解.
超声回弹综合法检测混凝土构件强度时,对于长度小于等于2m的构件,其测区数量可适当
在下列预测方法中,考虑了时间序列全部数据的预测方法是()。A:上期销售量法 B
选用钢弹簧隔振器的优点是( )。A.有较低的固有频率 B.不会产生共振激增
为抗击新型冠状病毒,武汉从2020年1月24日至2月2日在武
(2015年真题)居民是社区工作中最有价值的资源,与居民初次接触时,社会工作者要
人的身心发展是在{pz_填空}过程中实现的。
下列选项中属于建设工程静态投资的有()。A.建安工程费 B.价差预备费
最新回复
(
0
)