首页
登录
从业资格
The earned value technique is a commonly
The earned value technique is a commonly
练习题库
2022-08-02
53
问题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ) .A.he project is ahead of its planned scheduleB.less work was completed than was planned tC.the cost overrun for work completedD.the cost underrun of performance to date
选项
A.he project is ahead of its planned schedule
B.less work was completed than was planned t
C.the cost overrun for work completed
D.the cost underrun of performance to date
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299763.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
Ascheduleiscommonlyusedinprojectp
Theearnedvaluetechniqueisacommonly
Ethernetisthecommonlyusedlocalarea
Ethernetisthecommonlyusedlocalarea
()isaprojectmanagementtechniquefor
Aprojectmanagementtechniquethatisc
Theearnedvaluetechniqueisacommonly
Earnedvaluemanagement(EvM)integrates
Ethernetisthecommonlyusedlocalarea
随机试题
Whatarethemanandwomantalkingabout?[br][originaltext]W:Hello,James.C
Acupuncture(针灸)isbasedontheideathatenergyflowsthroughthehumanbody
在观察新药的有效作用时,研究人员搜集的数据是( )。A.一手观测数据 B.二
根据《党政机关公文处理工作条例》的相关要求,下列公文标题正确的是()(易错)
合剂的分散系统不包括A、混悬型 B、乳剂型 C、浸膏型 D、胶体型 E、
哥白尼的“太阳中心说”并非真正科学,但他的巨大进步意义在于()。A.为近代
建立()数据库是对操作风险进行定量分析的基础。A:风险诱因B:历史损失C:资
下列关于参与管理的说法中,错误的是()。A.参与管理就是让下属人员实际分享上级
根据企业所得税法律制度的规定,企业缴纳的下列税金中,在计算企业所得税应纳税所得额
(2014年)某项目拟建于占地面积为50km的围海造地规划工业园区内,距海岸5k
最新回复
(
0
)