首页
登录
从业资格
The earned value technique is a commonly
The earned value technique is a commonly
练习题库
2022-08-02
85
问题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ) .A.he project is ahead of its planned scheduleB.less work was completed than was planned tC.the cost overrun for work completedD.the cost underrun of performance to date
选项
A.he project is ahead of its planned schedule
B.less work was completed than was planned t
C.the cost overrun for work completed
D.the cost underrun of performance to date
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299763.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
Ascheduleiscommonlyusedinprojectp
Theearnedvaluetechniqueisacommonly
Ethernetisthecommonlyusedlocalarea
Ethernetisthecommonlyusedlocalarea
()isaprojectmanagementtechniquefor
Aprojectmanagementtechniquethatisc
Theearnedvaluetechniqueisacommonly
Earnedvaluemanagement(EvM)integrates
Ethernetisthecommonlyusedlocalarea
随机试题
【B1】[br]【B18】A、andB、orC、butD、thoughC前半句讲计算机当然可以做加法,后半句讲那只是对计算机非常有限的认识,可见此句
SpeakerA:Marywon’tbecomingtoworktomorrow.She’sfinallygoingtothephot
Itisnowclearthattheterminologyusedbyacultureprimarilyreflectst
2009年-2017年全国外商投资企业进出口总额及同比增速均高于上年的年
有助于鉴别再障与急性白血病的是A:感染发热 B:皮肤、黏膜出血 C:贫血苍白
水蛭最主要的性状特征是A.体圆,背部有黑色斑点散在,两端各具1吸盘 B.体扁平
A.1B.2C.3D.4E.5用于预防和治疗特殊疾病的中药可以实行保护的级别为几
《药品管理法》所规定的药品不包括A.中药材、中药饮片B.生化药物C.血清、疫苗D
请根据下面提供的单据完成关于《入境货物报检单》填制的单项选择题24—33题:
()为估算每个工作的持续时间提供了主要依据。A.工作属性 B.资源日历
最新回复
(
0
)