The earned value technique is a commonly

练习题库2022-08-02  41

问题 The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0,  it means that  ( ) .A.he project is ahead of its planned scheduleB.less work was completed than was planned tC.the cost overrun for work completedD.the cost underrun of performance to date

选项 A.he project is ahead of its planned schedule
B.less work was completed than was planned t
C.the cost overrun for work completed
D.the cost underrun of performance to date

答案 B

解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299763.html

最新回复(0)