Earned value management(EVM) integrates

免费题库2022-08-02  51

问题 Earned value management(EVM) integrates the scope baseline with the ()baseline,along with schedule baseline,to form the performance baseline,which helps the project management team assess and measure project performance and progress.A.qualityB.riskC.changeD.cost

选项 A.quality
B.risk
C.change
D.cost

答案 D

解析 挣值管理(EVM)将范围基线与(成本)基线以及进度基线集成在一起,形成性能基线,帮助项目管理团队评估和度量项目性能和进度。
A、质量
B、风险
C、变更
D、成本