Earned value management(EVM) integrates
Earned value management(EVM) integrates
免费题库
2022-08-02
95
问题
Earned value management(EVM) integrates the scope baseline with the ()baseline,along with schedule baseline,to form the performance baseline,which helps the project management team assess and measure project performance and progress.A.qualityB.riskC.changeD.cost
选项
A.quality
B.risk
C.change
D.cost
答案
D
解析
挣值管理(EVM)将范围基线与(成本)基线以及进度基线集成在一起,形成性能基线,帮助项目管理团队评估和度量项目性能和进度。
A、质量
B、风险
C、变更
D、成本
转载请注明原文地址:https://tihaiku.com/congyezige/2298205.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thehighestlevelofqualitymanagement
Inprojecttimemanagement,activitydef
Qualitymanagementensuresthatanorgan
Inprojectmanagementandsystemsengine
Humanresourcemanagementisthemanagem
ProjectIntegrationManagementincludes
( )managementincludesnegotiatingthe
TheProjectManagementTriangleisamod
Riskmanagementallowstheprojectmanag
()managementincludesnegotiatingthe
随机试题
[originaltext]PopeJohnPadinavisittoGermanyistryingtoeasethehist
[originaltext]M:Icouldn’tputupwithmywifeanylonger.Idon’tknowwhysh
EmilyDickinsonwasdifferentfromotherwomenofhergenerationinthatshe
下列表述中,不正确的是( )A.纤维素在酶的作用下被水解为纤维二糖,进而转化
共用题干 TheNeedtoRememberSomepeoplesa
【材料一】一日,王教授应邀到甲机关举办一场关于职业道德与行为规范关系的专题讲座。
证券公司集合资产管理计划在任一时点,持有的卖出股指期货合约价值总额不得超过集合资
某水利水电工程受弯构件,受压区受力钢筋采用绑扎接头,则同一截面内钢筋接头面积占受
男,40岁,近半年反复出现尿频、尿急、尿痛,排尿时尿道灼热。并伴有性功能减退,出
男,52岁。突发呼吸困难4小时。既往糖尿病、高血压病史10年。查体:R32次/
最新回复
(
0
)